Question
24 male working 12 hours per day
can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which of the following statements is/are correct? I. 12 male and 16 female, working 5 hours a day, will complete the work in 86.4 days. II. If a Manager is 20% more efficient than a female, then 25 Manager and 5 male, working 6 hours a day, will finish the work in 72 days. III. If 5 male and 7 female together finish the work and are paid a total of Rs. 1,360, then the total amount received by the male is Rs. 800.Solution
ATQ, Let the efficiency of a male and a female be 'M' and 'F' units/day, respectively. 24 X 12 X 30 X M = 36 X 8 X 60 X F Or, M:F = 2:1 Let 'M' = '2e' and 'F' = '1e' Total work = 24 X 12 X 30 X 2e = '17,280e' units Statement I: Required time = 17280e Ă· [(12 X 2e + 16 X 1e) X 5] = 86.4 days So, statement I is true. Statement II: Efficiency of a Manager = 1.2 X 1e = '1.2e' Required time = 17280e Ă· [(25 X 1.2e + 5 X 2e) X 6] = 72 days So, statement II is true Statement III: Ratio of amount received by all the male together to that received by all the female together = (5 X 2e) :7e = 10:7 Required amount = (10/17) X 1,360 = Rs. 800 So, statement III is true. Therefore, all statements I, II and III are true.
Who is the Minister of Civil Aviation?
The ______ in China is the world’s longest man-made waterway.
Ravi Mittal Has been recently appointed as the chairman of IBBI. when was it established?
The state flower of Haryana is ______.
Where is the Headquarters of the International Atomic Energy Agency (IAEA)?
Match List-I with List-II and choose the correct answer from the codes given below:
Find the correct statement/s about SFURTI scheme which was lunched with the view to promote Cluster development.
...Ranikhet disease of fowl is spread through
What year marked the launch of the Beti Bachao Beti Padhao (BBBP) initiative?
Which Indian state recently celebrated its 56th liberation day to commemorate its independence from Portugese rule