Question
24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which of the following statements is/are correct?
24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which of the following statements is/are correct?
I. 12 male and 16 female, working 5 hours a day, will complete the work in 86.4 days.
II. If a Manager is 20% more efficient than a female, then 25 Manager and 5 male, working 6 hours a day, will finish the work in 72 days.
III. If 5 male and 7 female together finish the work and are paid a total of Rs. 1,360, then the total amount received by the male is Rs. 800.
More Time and work Questions
- X men can complete the piece of work in 45 days and (X + 46) men can complete the same work in 23 days less than that of days taken by X men. Find the valu...
- Efficiency of a man is 25% more than that of a woman. (2n + 4) men working 8 hours a day can complete a task in 18 days, whereas (3n - 2) women working 6 h...
- The efficiency of C is 20% more than the efficiency of D. D alone can complete a piece of work in (y-2) days. The time taken by C alone to complete the wor...
- A and B together can do a work in 5 days. If A can alone do the same work in 15 days, then in how many days B alone will do the same work?
- Nikhil and Rohit together can complete a job in 105 days 8 minutes, while Rohit and Suresh together can finish the same job in 70 days 5 minutes. If Suresh...
- A group of 21 boys, each working 6 hours a day, complete a school project in 15 days. How many days will it take for 18 boys, working 5 hours daily, to fin...
- ‘Pooja’ alone can finish a piece of work in 60 days. After working for 36 days, she left the job. ‘Vikram’ then completed the rest in 12 days. How many day...
- A fence is constructed using 900 wooden planks. ‘X’ alone can place 10 planks per minute, while ‘Y’ alone can complete the fence in 100 minutes. ‘Z’, a cur...
- ‘A’ can do a piece of work in 15 days. ‘B’ can do 60% of the same work in 20 days. If they work together for the entire time and get paid Rs.1450, then fin...
- 25 men and 45 women can complete a piece of work in 15 days, while 15 men and 60 women can complete it in 20 days. In how many days can 69 men and 67 women...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)