Question

24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which of the following statements is/are correct?
I. 12 male and 16 female, working 5 hours a day, will complete the work in 86.4 days.
II. If a Manager is 20% more efficient than a female, then 25 Manager and 5 male, working 6 hours a day, will finish the work in 72 days.
III. If 5 male and 7 female together finish the work and are paid a total of Rs. 1,360, then the total amount received by the male is Rs. 800.

A Only II
B Only I and II
C Only I
D Only III and II
E All I, II and III