Question
Ravi can complete a task alone in 12 days. After a few
days, Mohan joins him and both complete the remaining 50% of the work in 3 days. How long will Mohan alone take to complete the entire work?Solution
ATQ, Let the efficiency of Ravi be 'x' units/day. So, total work = 12 × x = 12x units So, work done by Ravi and Mohan together = 12x × 0.5 = 6x units So, combined efficiency = 6x ÷ 3 = 2x units/day So, efficiency of Mohan = 2x - x = x units/day So, required time = 12x ÷ x = 12 days
Which of the following factors can influence the progression of the Innovation Life Cycle?
1. Market dynamics
2. Regulatory compliance
...Which of the following statements is correct regarding Intellectual Property rights?
Identify the incorrect statement(s) about the types of innovation :
Which of the following statements about the innovation life cycle is/are correct?
1. All innovation life cycles follow the same timeline regardle...
__ the process of collection, compilation and analysis of economic data for the purpose of finding out possible opportunities for investment.
Which statement(s) about Startups is/are incorrect ?
Which of the following statements about MeitY's Centres of Excellence (CoEs) is/are correct?
1. CoEs are operationalized with the participation o...
What is a significant advantage of working in a startup?
Which among the following aspects affects an entrepreneur’s perception of feasibility?
Which of the following is NOT a feature of innovative leadership?