Question
The efficiency ratio of D, E, and F is 1:2:5. Together, they complete a project in 16 days. If D and E contribute for 14 days and leave, how long will F take to complete what's left?
More Time and work Questions
- A pipe can fill a tank in 14 hours, and B pipe can drain a tank in 21 hours. If a system of N pipes (fill pipes and drain pipes put together) can fill the ...
- A group of 36 boys works 13 hours per day and completes 37.5% of a task in 20 days. After these 20 days, 'X' boys leave the job. The remaining boys continu...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 10 t...
- Rahul, Rohit, and Raj alone can complete a project in 40, 80, and 120 days respectively. All of them started working together, but after 10 days, Rahul lef...
- Farhan and Dev can complete a work alone in 75 days and 90 days respectively. If they work together and earn Rs. 8,250, find Dev’s share.
- P, Q and R can do some work in 11 days, 20 days and 55 days respectively. In how many days can the work be done, if P gets the assistance of Q and R on alt...
- A and B can complete a work together in 36 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
- ‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 30 hours. If ‘B’ completed the rest of the work in 2...
- There is enough food in a camp to last for 60 days if each of the 20 soldiers present at the camp eat 5 times a day. After 30 days, 10 more soldiers joined...
- 50 workers working 6 hours a day take 18 days to complete a task. How many workers working for 5 hours a day are needed to complete four times the given ta...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt