📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      A can complete a task in 10 days, and B can complete it

      in 15 days. After 3 days of working together, B leaves. How many more days will A take to finish the remaining work?
      A 3 Correct Answer Incorrect Answer
      B 4 Correct Answer Incorrect Answer
      C 5 Correct Answer Incorrect Answer
      D 6 Correct Answer Incorrect Answer

      Solution

      Combined 1-day work of A and B = 1/10 + 1/15 = 1/6 Work done in 3 days = 3 × 1/6 = 1/2 Remaining work = 1/2 A’s 1-day work = 1/10 Days taken by A = (1/2)/(1/10) = 5 days

      Practice Next
      ask-question