πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    ⚑ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug ⚑ Enroll Now

    Question

    A can complete a task in 10 days, and B can complete it

    in 15 days. After 3 days of working together, B leaves. How many more days will A take to finish the remaining work?
    A 3 Correct Answer Incorrect Answer
    B 4 Correct Answer Incorrect Answer
    C 5 Correct Answer Incorrect Answer
    D 6 Correct Answer Incorrect Answer

    Solution

    Combined 1-day work of A and B = 1/10 + 1/15 = 1/6 Work done in 3 days = 3 Γ— 1/6 = 1/2 Remaining work = 1/2 A’s 1-day work = 1/10 Days taken by A = (1/2)/(1/10) = 5 days

    Practice Next
    More Time and work Questions
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call