Question
A company hires workers A, B, and C to finish a project.
A can complete the project in 30 days, B can do it in 24 days, and C can complete it in 20 days. They start working together, but after 5 days, A leaves. How many more days will B and C together take to finish the remaining work?Solution
Work done by A, B, and C in 1 day = 1/30 + 1/24 + 1/20 = 4/120 + 5/120 + 6/120 = 15/120 = 1/8 of the project per day. Work completed by all in 5 days = 5 × 1/8 = 5/8 of the project. Remaining work = 1 - 5/8 = 3/8 of the project. Work done by B and C together in 1 day = 1/24 + 1/20 = 5/120 + 6/120 = 11/120 of the project per day. Time taken by B and C to finish the remaining 3/8 work = (3/8) ÷ (11/120) = 3/8 × 120/11 = 45/11 = 4.09 days.= 4 days(approx)
A soil is low in available N if the soil organic carbon is in the range of
Jam and jellies are mainly spoiled by
Trickling bed is terminology used in
Under given pest, BT cotton shows resistant to?
Lopping is related to?
In hill soils or acidic soils, nutrients are present except?
Capacity is the second "C" of 3°C of credit, which indicates (A) (C) (E)
In which housing system, repeated spreading of straw or sawdust material in indoor booths. An initial layer of litter is spread for the animals to us...
Which of the following weed species causes a major threat to sorghum production?
Where the Directorate of plant Protection quarantine & storage is situated