Question
A company hires workers A, B, and C to finish a project.
A can complete the project in 30 days, B can do it in 24 days, and C can complete it in 20 days. They start working together, but after 5 days, A leaves. How many more days will B and C together take to finish the remaining work?Solution
Work done by A, B, and C in 1 day = 1/30 + 1/24 + 1/20 = 4/120 + 5/120 + 6/120 = 15/120 = 1/8 of the project per day. Work completed by all in 5 days = 5 Γ 1/8 = 5/8 of the project. Remaining work = 1 - 5/8 = 3/8 of the project. Work done by B and C together in 1 day = 1/24 + 1/20 = 5/120 + 6/120 = 11/120 of the project per day. Time taken by B and C to finish the remaining 3/8 work = (3/8) Γ· (11/120) = 3/8 Γ 120/11 = 45/11 = 4.09 days.= 4 days(approx)
- Find the least 5-digit number which leaves no remainder when divided by 22, 33, 44 and 66.
- The largest 5-digit number which is exactly divisible by β47β is:
Group βMβ comprises four even integers in order, and group βNβ includes four successive odd integers. If the average of their first elements is ...
How many Zeros can be formed by multiplying 10×20×30×40×…………….× 100
Which of the following is the greatest number that divides 72 and 119 and leaves 3 and 4 as respective remainders?
The difference between the squares of two positive numbers is 18 times the difference between the numbers. If the smaller number is 7, then what is the ...
The value of
3 chairs and 2 tables cost Rs. 700 and 5 chairs and 3 tables cost Rs. 1100. What is the cost of 1 chair and 2 tables?
In a particular examination, Cheenu achieved 48% of the total marks and fell short by 72 marks to pass. On the other hand, Meenu obtained 68% of the tot...
Find the largest three-digit number that leaves '3', '4' and '5' as remainder when it is divided by '7', '8' and '9', respectively.