Question
Amit, Bheema, and Chetna can
finish the task in 32 days, 24 days, and 30 days respectively. If they start the task together, and Bheema leaves 12 days before the task is completed while Chetna leaves 6 days before the task is completed, in how many total days will the task be finished?Solution
ATQ, Let the total task be done in 'd' days d/32 + (d β 12)/24 + (d β 6)/30 = 1 15d + 20d β 240 + 16d β 96 = 480 d = 16
β256 * 3 β 15% of 300 + ? = 150% of 160
(5.6 + 2.4 + 13.8 β 2.8) Γ 5 = ? Γ (12.5 β 7.5)
Solve: 3/4Γ·2/3 β
(292 β 141) Γ· 5 + (40 Γ· 2) + 23 = ?
(26)2 = {(20% of 40% of 18200) Γ· ?} Γ 1664 Γ· 128Β
- What will come in place of (?) in the given expression.
(18.5 Γ 2) + (3.5 Γ 4) = ? What will come in the place of question mark (?) in the given expression?
48 X 2.5 + 20% of 150 = ? + 166
166/? = √576 - 3.25
[(36 Γ 15 Γ· 96 + 19 Γ· 8) Γ 38] = ?% of 608