Question
Amit, Bheema, and Chetna can finish the task in 32 days, 24 days, and 30 days respectively. If they start the task together, and Bheema leaves 12 days before the task is completed while Chetna leaves 6 days before the task is completed, in how many total days will the task be finished?
More Time and work Questions
- ‘A’ alone can complete a piece of work in 30 days while ‘A’ and ‘B’ together can complete the same work in 20 days. ‘B’ started the work and after 4 days ‘...
- A work can be completed by ‘A’ and ‘B’, alone in 7 days and 14 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ...
- A is twice as efficient as B. Together they can complete a work in 18 days. In how many days can A alone complete the work?
- A does 2/5 of a work in 9 days. Then B joined him and they together completed the remaining work in 6 days. B alone can finish the whole work in
- Three boys can do a work in 15 days where as 6 girls can do in 12days. What will be the time taken to complete the same work by a teacher if the efficiency...
- Working 10 hours a day, Jagan can complete a work in 12 days while working 8 hours a day, Magan can complete the same work in 9 days. If Jagan and Magan wo...
- P can construct a robot individually in 20 hours, while Q requires 40 hours to complete the same task. If they collaborate, how many hours will it take the...
- A and B together can do a piece of work in (p-8.8) days.The efficiency of D is 10% less than the efficiency of B. A and C together can do the same piece of...
- A is thrice as efficient as B and can finish a piece of work in 28 days less than B. B can finish this work in how many days?
- Three workers A, B and C can complete a job in 12, 15 and 20 days respectively, working alone. All three start working together. After some time, C leaves,...