Question
Amit, Bheema, and Chetna can
finish the task in 32 days, 24 days, and 30 days respectively. If they start the task together, and Bheema leaves 12 days before the task is completed while Chetna leaves 6 days before the task is completed, in how many total days will the task be finished?Solution
ATQ, Let the total task be done in 'd' days d/32 + (d β 12)/24 + (d β 6)/30 = 1 15d + 20d β 240 + 16d β 96 = 480 d = 16
Which is not the function of the Operating System?
Aman bought a goat and a hen, with the goat's cost price being βΉ1200 more than the hen's. He sold the hen at a 20% loss and the goat at a 25% profit, ...
10, 11, 7, 34, 18, 125
In the above given series, there is a wrong term. Find the 4th term of another series whose first term is the wrong number...
How many possible values can the digit 'k' take if the number 9458k2 is divisible by 8?
A sum of money becomes βΉ7800 after 3 years and βΉ8500 after 4 years at simple interest. What is the principal amount?
In a 1500-metre race, Arjun beats Bishnu by 600 metres, and Bishnu beats Chintu by 700 metres. How far will Arjun beat Chintu by ...
(78.03 + 116.98) Γ· 13.211 = 89.9 β 25.23% of ?
A trader buys a stock at an average price of Rs. 240 per share. He sells one-third of his shares at a 10% profit and the remainin...
Anuj invested a certain amount for 18 months at a simple interest rate of 5% per annum and received a total of Rs. 3,440. What wo...
The mean and standard deviation of 6 observations are 10 and 3 respectively. If each observation is multiplied by 4 and then 5 is added to each result, ...