Question

Amit, Bheema, and Chetna can finish the task in 32 days, 24 days, and 30 days respectively. If they start the task together, and Bheema leaves 12 days before the task is completed while Chetna leaves 6 days before the task is completed, in how many total days will the task be finished?

A 24
B 12
C 08
D 16
E None of these