πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A, B and C alone can complete a work in 18, 32 and 24

      days respectively. All of them started working together but after 3 days from start A left the job and after 5 more days B also left the job. So for how many days did C work?
      A 12.5 days Correct Answer Incorrect Answer
      B 26 days Correct Answer Incorrect Answer
      C 14 days Correct Answer Incorrect Answer
      D 25 days Correct Answer Incorrect Answer
      E 33 days Correct Answer Incorrect Answer

      Solution

      Let the total work = 288 units (LCM of 18, 32 and 24) Amount of work done by A alone in one day = 288/18 = 16 units Amount of work done by B alone in one day = 288/32 = 9 units Amount of work done by C alone in one day = 288/24 = 12 units Amount of work done by A, B and C together in 3 days = 3 Γ— (16 + 9 + 12) = 111 units Amount of work done by B and C together in 5 days = 5 Γ— (9 + 12) = 105 units Remaining work = 288 – 111 – 105 = 72 units So, the time taken by C alone to complete 72 units work = 72/12 = 6 days So, C worked for 6 + 3 + 5 = 14 days

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question