Question
A can complete a piece of work in 12 days and B can
complete the same work in 18 days. They work together for 4 days and then leave the remaining work to C, who finishes it in 6 days. In how many days can C alone complete the entire work?Solution
Assume total work = LCM of 12 and 18 = 36 units Aβs 1-day work = 36/12 = 3 units Bβs 1-day work = 36/18 = 2 units (A + B)βs 1-day work = 3 + 2 = 5 units Work done in first 4 days: = 5 Γ 4 = 20 units Remaining work = 36 β 20 = 16 units Let Cβs 1-day work = x units C finishes 16 units in 6 days: 6x = 16 x = 16/6 = 8/3 units per day Time taken by C to complete full work: = 36 / (8/3) = 36 Γ (3/8) = 108 / 8 = 13.5 days
A and B together can complete a work in 7.2 days, while B and C together can complete the same work in 12 days. If A is twice efficient than C, then fin...
'K' and 'L' together can complete a work in 24 days. They started working together but after 16 days, 'L' left and remaining work was completed by 'K' a...
P, Q, and R can do a project individually in 10, 25, and 20 days. P and Q begin the project, but after 2 days, P is replaced by R. How many more days wi...
Efficiency of a man is 25% more than that of a woman. (n - 10) men working 6 hours a day can complete a task in 18 days, whereas (n - 9) women working ...
'Asmita,' who is three times as efficient as 'Bittu,' can complete a task on her own in 15 days. 'Asmita' and 'Bittu' began working together, but after ...
Three men and 4 women can do a piece of work in 7 days, whereas 2 men and I woman can do it in 14 days. Seven women will complete the same work in:
- Sonia and Riya decided to complete a piece of work together. Sonia is capable of doing 9 units of work per day, whereas Riya can finish the complete task a...
A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after βxβ days, after whic...
βRβ and βSβ can together finish a job in 18 days. If βRβ alone can finish it in 30 days, how many days will βSβ alone take?
...- Two pipes X and Z can fill a tank in 36 hours and 48 hours respectively, while pipe Y can drain the tank in 72 hours. If pipes X and Z are opened together ...