Question
30 men can complete a task in 160 days. 12 men start the work and manage to do half of it. Then, 18 more men are added to the team to help finish the work. Find the total duration required to complete the task.
More Time and work Questions
- A and B individually can complete the work in 28 days and 42 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed th...
- X men can complete the piece of work in 36 days and (X + 35) men can complete the same work in 14 days less than that of days taken by X men. Find the valu...
- If one man or two women or four boys or five girls can finish a work in 39 days, then how many days will one man, one woman, one boy and one girl together ...
- Together, Ali and Imran take 40 days to complete a project. After working jointly for 32 days, they left, and Zara completed the remaining work in 4 days. ...
- Person A can complete 25% of a job in 4 days. Person B is 20% less efficient than Person A. How many days will it take for both A and B, working together, ...
- ‘A’ is 25% more efficient than ‘B’. ‘A’ and ‘B’ work together for 5 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 5 more days to finis...
- Pooja can complete a task in 45 days and Kavita in 30 days. A third person, Mehul, is 20% more efficient than both of them combined. How many days will Meh...
- Workers A and B can finish a task in 30 days when working together. They worked for 18 days, and then C completed the rest of the task alone in 12 days. Ho...
- ‘P’ can finish a task in 36 days, while ‘Q’ can do the same task in (x + 4) days. If both work together and finish the task in 12 days, what is the value o...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt