Question
30 men can complete a task in 160 days. 12 men start the
work and manage to do half of it. Then, 18 more men are added to the team to help finish the work. Find the total duration required to complete the task.Solution
ATQ, Total amount of work = (30 x 160) = 4800 units Amount of work completed by 12 men = (4800/2) = 2400 units Time taken by 12 men to complete half of the work = (2400/12) = 200 days Amount of work completed by 30 men (12 + 18) = 4800 - 2400 = 2400 units Time taken by 30 men to complete 2400 units = (2400/30) = 80 days Total time taken = 200 + 80 = 280 days
Sultan Abu Bakr Shah was from which of the following dynasties?
The United Nations Conference on Environment and Development (UNCED) took place at _______ in the year_______
 Convention on biological diver...
According to the 73rd amendment of the Constitution of India, what is the minimum age prescribed for the election of a member of a Panchayat?
Lohit River flows in?
- Which Indian ruler signed the Treaty of Bassein with the British East India Company in 1802?
In case of dispute between two Panchayats, the dispute is finally settled by whom?
Which of the following Articles of the Indian Constitution deal with cultural and educational rights?
Which article describe freedom as the payment of taxes for promotion of any particular religion?
Select the option that shows the correct arrangement of the given words in the order in which they appear in the English dictionary.Â
1. Feather...
Which pair is not correctly matched?