Question
30 men can complete a task in 160 days. 12 men start the
work and manage to do half of it. Then, 18 more men are added to the team to help finish the work. Find the total duration required to complete the task.Solution
ATQ, Total amount of work = (30 x 160) = 4800 units Amount of work completed by 12 men = (4800/2) = 2400 units Time taken by 12 men to complete half of the work = (2400/12) = 200 days Amount of work completed by 30 men (12 + 18) = 4800 - 2400 = 2400 units Time taken by 30 men to complete 2400 units = (2400/30) = 80 days Total time taken = 200 + 80 = 280 days
P is the father of S, whose mother is Q. R is the sister of Q. What does P's father-in-law have to relate to R's husband?
What would be the word on the opposite side of 'Eat' if the given sheet is folded to form a cube?
Select the missing number from the given series.
41, 83, 168, 339,?
What will come in the place of β?β in the following equation, if β+β and βΓ·β are interchanged and βΓβ and βββ are interchanged?<...
Change the question mark with the option that follows the logic applied to the first pair.
2018 : 22 :: 2022 : ??
Six persons P1, P2, P3, P4, P5 and P6 are sitting around a circular table facing towards the centre (not necessarily in the same order). Only two person...
Select the option which is related to the fifth letter-cluster in the same way as the second letter-cluster is related to the first letter-cluster and t...
A @ B means A is the sister of B:
A # B means A is the father of B:
A & B means B is the wife of A.
Based on the above information,...
Select the figure that will replace the question mark (?) in the following figure series.
The two statements in this question and the two conclusions related to them are given in the form of i and ii, assuming that the statements given in the...