Question
30 men can complete a task in 160 days. 12 men start the
work and manage to do half of it. Then, 18 more men are added to the team to help finish the work. Find the total duration required to complete the task.Solution
ATQ, Total amount of work = (30 x 160) = 4800 units Amount of work completed by 12 men = (4800/2) = 2400 units Time taken by 12 men to complete half of the work = (2400/12) = 200 days Amount of work completed by 30 men (12 + 18) = 4800 - 2400 = 2400 units Time taken by 30 men to complete 2400 units = (2400/30) = 80 days Total time taken = 200 + 80 = 280 days
The teacher advised me that I should practice as much as I can if I wanted to score 100% marks in Mathematics.
The teacher asked Avika what had happened to her and why her nose was bleeding.
Select the most appropriate indirect form of the given sentence.
“What sort of a house are you looking for, Mr. Barrington?” said the house...
Select the option that expresses the given sentence in reported speech.
Addressing the nation, the President said, "There are some days when we...
Select the most appropriate direct form of the given sentence.
The customer asked the shopkeeper how much she had to pay for the little glass table.
Select the option which correctly converts the given sentence into direct speech.
I asked him if it had never occurred to him that even the meane...
My son said to me, "I will not disappoint you."
The officer ordered the fellow to be arrested.
Choose the option that is the direct form of the sentence.
He asked me to wait there until I got my turn.
The child said, "What a beautiful sight!"