ATQ, Total amount of work = (30 x 160) = 4800 units Amount of work completed by 12 men = (4800/2) = 2400 units Time taken by 12 men to complete half of the work = (2400/12) = 200 days Amount of work completed by 30 men (12 + 18) = 4800 - 2400 = 2400 units Time taken by 30 men to complete 2400 units = (2400/30) = 80 days Total time taken = 200 + 80 = 280 days
Photorespiration involves
Which one of the following developed Indore method of composing?
The word "Agronomy" has originated from.....................?
Which seed class is associated with a golden yellow tag in India?
An economy where allocation of resources is determined by the operation of price mechanism is termed as:
Carbamate and organophosphate insecticide act on which part of insects?
Cowpox disease is caused by which organism?
Which reptile is characterized by the presence of four-chambered heart?
Intense leaching and weathering of bases like Ca, Mg result for development of which type of soil?
The yield of forest is regulated on the basis of volume by using following: