30 men can complete a task in 160 days. 12 men start the work and manage to do half of it. Then, 18 more men are added to the team to help finish the work. Find the total duration required to complete the task.
ATQ, Total amount of work = (30 x 160) = 4800 units Amount of work completed by 12 men = (4800/2) = 2400 units Time taken by 12 men to complete half of the work = (2400/12) = 200 days Amount of work completed by 30 men (12 + 18) = 4800 - 2400 = 2400 units Time taken by 30 men to complete 2400 units = (2400/30) = 80 days Total time taken = 200 + 80 = 280 days
The lateral surface area of a cube is 144 cm2 . The length of a cuboid is 25% more than the side of the cube. The breadth of the cuboid is 5 ...
The ratio of length to breadth of a rectangle is 5:4, respectively. Perimeter of rectangle is 234 cm. If each side of a square is 25% more than the brea...
The length, breadth and height of a room are in the ratio 7:5:2. If the breadth and height are halved while the length is doubled, then the total area o...
Perimeter of a square field is 120 meters and the area of a rectangular field is 20% more than that of the square field. Find the area (in m2...
The value of (sin23° / cos67°) + (cos71° / sin19°) is:
The area of four walls of a room is 192 cm2. If the length and breadth of the room were equal and the height of the room is 6 cm, then what i...
The total population of a village is 1000. The number of males and females increases by 6% and 8% respectively and consequently the population of the vi...
For a positive integer n, 25n – 52n is divisible by:
The capacity of a cylindrical tank is 2376 m³. If the radius of the tank is 21 m, then the depth of the tank is:
If the areas of three adjacent faces of a rectangular box which meet in a corner are 12cm2, 15cm2 and 20cm2 respective...