Question
30 men can complete a task in 160 days. 12 men start the
work and manage to do half of it. Then, 18 more men are added to the team to help finish the work. Find the total duration required to complete the task.Solution
ATQ, Total amount of work = (30 x 160) = 4800 units Amount of work completed by 12 men = (4800/2) = 2400 units Time taken by 12 men to complete half of the work = (2400/12) = 200 days Amount of work completed by 30 men (12 + 18) = 4800 - 2400 = 2400 units Time taken by 30 men to complete 2400 units = (2400/30) = 80 days Total time taken = 200 + 80 = 280 days
The Legend of Lakshmi Prasad by Twinkle Khanna is a compilation of 4 distinct short stories, one of them being inspired by real life.
Who is the author of the book ‘Courts of India: Past to Present’?
The beneficiaries under the Integrated Child Development Services (ICDS) Scheme are children in the age group of:
Where is Duncan passage located?Â
What was the code name given by Indian Air Force for February 2019 surgical Strike on Balakot?Â
Which of the following Indian musicians was referred to as ‘Ghazal King’?
In the following question, select the missing number from the given alternatives.
45, 15, 60, 75, 135, ?
In June 2020, Amit Panghal and Vikas Krishan were nominated for ______ by the Boxing Federation of India.
Where will the first IIT campus outside India be established to expand the reach of the Indian Institutes of Technology (IITs)?
Consider the following statements about e-Shakti initiate of the Government of India:
1. e-Shakti is a pilot project of National Bank for Agricul...