Question
Akhil and Nikhil together can complete a work in 12 days
while Nikhil alone takes 18 days to complete 25% of the work. If the efficiency of Sachin is 20% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.Solution
Time taken by Nikhil to complete the whole work alone = 18/0.25 = 72 days Let the total work = 72 units Efficiency of (Akhil + Nikhil) = 72/12 = 6 units/day Efficiency of Nikhil = 72/72 = 1 units/day Efficiency of Akhil = 6 - 1 = 5 units/day Therefore efficiency of Sachin = 1.20 x 5 = 6 units/day Time taken by Sachin to complete the whole work alone = 72/6 = 12 days
     I.       Foreign Direct Investment (FDI) has been on the rise , A. with foreign companies investing B. in various C. sectors of the I...
- In the questions given below, a sentence has been divided into four fragments (A), (B), (C) and (D) and is arranged (not necessarily in the correct order)....
In each of the questions given below a sentence is given with three words in bold. Choose the option which gives the correct sequence of these words to ...
Which of the following will be the FIFTH (last) sentence after the rearrangement?
- Parts of a sentence are given below in jumbled order. Arrange the parts in the correct order to form a meaningful sentence.
(P) more than three dec... Rearrange the following sentences in the proper sequence to form a meaningful paragraph and then answer the questions given below.
A. These bea...
Each question is divided into four parts a,b,c,d. In some questions they are not in the sequence so according to grammar and context re- arrangement is...
- In the following questions, each question is divided into four parts. Rearrange the following parts into a meaningful sentence and mark the option accordin...
Which of the following is the fifth sentence of the passage?
In each of the questions given below a sentence is given with three words in bold. Choose the option which gives the correct sequence of these words to ...