📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    ⚡ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug ⚡ Enroll Now

    Question

    Akhil and Nikhil together can complete a work in 12 days

    while Nikhil alone takes 18 days to complete 25% of the work. If the efficiency of Sachin is 20% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.
    A 12 days Correct Answer Incorrect Answer
    B 10 days Correct Answer Incorrect Answer
    C 20 days Correct Answer Incorrect Answer
    D 15 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Time taken by Nikhil to complete the whole work alone = 18/0.25 = 72 days Let the total work = 72 units Efficiency of (Akhil + Nikhil) = 72/12 = 6 units/day Efficiency of Nikhil = 72/72 = 1 units/day Efficiency of Akhil = 6 - 1 = 5 units/day Therefore efficiency of Sachin = 1.20 x 5 = 6 units/day Time taken by Sachin to complete the whole work alone = 72/6 = 12 days

    Practice Next
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call