Question
Akhil and Nikhil together can complete a work in 12 days
while Nikhil alone takes 18 days to complete 25% of the work. If the efficiency of Sachin is 20% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.Solution
Time taken by Nikhil to complete the whole work alone = 18/0.25 = 72 days Let the total work = 72 units Efficiency of (Akhil + Nikhil) = 72/12 = 6 units/day Efficiency of Nikhil = 72/72 = 1 units/day Efficiency of Akhil = 6 - 1 = 5 units/day Therefore efficiency of Sachin = 1.20 x 5 = 6 units/day Time taken by Sachin to complete the whole work alone = 72/6 = 12 days
Firoj was in which of the following rows?
Who belongs to America?
Which of the following statements is correct?
How many boxes are placed below box X?
Four of the following five are alike in a certain way as per the given arrangement and thus form a group. Who among the following one does not belong t...
How many person(s) were born between Ganesh and Manju?
Who among the following person lives in flat 2 of floor 4?
Which of the following combination is definitely correct?
Who sits third to the right of T?
How many tests are scheduled between tests of Q and T?