    Akhil and Nikhil together can complete a work in 15 days

    while Nikhil alone takes 20 days to complete 50% of the work. If the efficiency of Sachin is 20% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.
    A 12 days Correct Answer Incorrect Answer
    B 10 days Correct Answer Incorrect Answer
    C 20 days Correct Answer Incorrect Answer
    D 15 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Time taken by Nikhil to complete the whole work alone = 20/0.50 = 40 days Let the total work = 120 units Efficiency of (Akhil + Nikhil) = 120/15 = 8 units/day Efficiency of Nikhil = 120/40 = 3 units/day Efficiency of Akhil = 8 - 3 = 5 units/day Therefore efficiency of Sachin = 1.20 x 5 = 6 units/day Time taken by Sachin to complete the whole work alone = 120/6 = 20 days