Question
Amit and BK working together can finish a particular
task in 90 days, while BK and Chiku working together can complete the same task in 70 days. Determine the number of days it would take for Amit to complete 80% of the task individually, given that Amit is 40% less efficient than Chiku.Solution
ATQ, Let the total work be 630 units. (LCM of 90 and 70) Amount of work done by Amit and BK together in one day = 630/90 = 7 units Amount of work done by BK and Chiku together in one day = 630/70 = 9 units Difference between the efficiencies of Amit and Chiku = 9 – 7 = 2 units Amount of work done by Chiku alone in one day = 2/0.40 = 5 units Amount of work done by Amit alone in one day = 0.6 × 5 = 3 units Time taken by Amit alone to complete 80% work = 0.8 × (630/3) = 168 days
Where are the headquarters of the International Air Transport Association (IATA)?
Who was the founder of the Banaras Hindu University (BHU) in Varanasi?
The percentage of deposits that a bank must keep as cash reserves with itself is known as ____?
Evaluate the following statements regarding Vikram-1 rocket:
- (I) Vikram-1 rocket is developed by Agni Cosmos.
- (II) Vikram-1 is a multi...
Recently the International Narcotics Control Board has highlighted the availability of drugs in the illicit market due to drug trafficking. In which yea...
- What was the name of the 25% land revenue tax collected by Marathas in the Deccan?
Under which article of the Constitution, the Allahabad High Court has recently declared the UP Board of Madrasa Education Act 2004 unconstitutional?
- When did Mahatma Gandhi initiate the 'Salt Satyagraha'?
Who has been appointed as the new Governor of Assam?
'Man -Yi' a super typhoon has hit which of these countries recently?