πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A, B and C can mow a field in 36 days, 72 days and 54

      days respectively. All the three began the work together on January 1, 2016, but A left 8 days and C 12 days before the completion of the work. If B took the rest for 4 days, then in how many days the work was finished from the day it started?
      A 26 Jan 2016 Correct Answer Incorrect Answer
      B 24 Jan 2016 Correct Answer Incorrect Answer
      C 28 Jan 2016 Correct Answer Incorrect Answer
      D 29 Jan 2016 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let work be completed in x days. Then, Work done by A in (x-8) days + work done by B in x days + work done by C in (x-12) days = 1 (x-8)/36 + x/72 + (x-12)/54= 1 ⇒(6(x-8)+ 3x+4(x-12))/216 = 1⇒(6x-48+3x+4x-48)/216 = 1 ⇒(13x-96)/216 = 1 ⇒ 13 x – 96 = 216 ⇒ 13 x = 312 ⇒x = 24 days ∴ Total days = 24 days Since B takes rest for 4 days, so the number of days in which the work was finished from the day it started = 24 + 4 = 28 i.e., on 28th January 2016.

      Practice Next
      ask-question