12 men can finish a work in 20 days by working 6 hours
a day. How many more men are needed to finish the work in 12 days by working 6 hours a day?Solution
Let the efficiency of a man be 'x' units/day. Let number of extra men needed to finish the work be 'y'. ATQ; Total work = (12 + y) × x × 12 × 6 = 12 × x × 20 × 6 Or, 12 + y = 20 So, y = 20 − 12 = 8 Therefore, the number of extra men required = y = 8
- Which state government organized the Global India Summit 2025?
Noma disease primarily affects which part of the human body?
Duncan Passage is a strait in the Bay of Bengal which separates little Andaman and ______________ .
- WHO has partnered with which country to launch a malnutrition initiative in Socotra Island, Yemen?
- Which state launched the Brindavan Gram Scheme and the Gita Bhavan Project to promote rural development and cultural heritage?
- Fire altars were found in which Harappan cities?
- Which pigment is primarily responsible for human skin color?
Which of the following statements is/are correct?
1. Baishakhi marks the beginning of Hindu Solar New year.
2. Baisakhi is the day wh...
Which ancient city in Uttar Pradesh is known as the oldest continuously inhabited city in the world?
Match the films with their categories: