      Question

      12 men can finish a work in 20 days by working 6 hours a day. How many more men are needed to finish the work in 12 days by working 6 hours a day?

      A 6 Correct Answer Incorrect Answer
      B 8 Correct Answer Incorrect Answer
      C 10 Correct Answer Incorrect Answer
      D 12 Correct Answer Incorrect Answer

      Solution

      Let the efficiency of a man be 'x' units/day. Let number of extra men needed to finish the work be 'y'. ATQ; Total work = (12 + y) Γ— x Γ— 12 Γ— 6 = 12 Γ— x Γ— 20 Γ— 6 Or, 12 + y = 20 So, y = 20 βˆ’ 12 = 8 Therefore, the number of extra men required = y = 8