Question
βAβ and βBβ together can complete a work in 18
days. If βAβ increases his efficiency by 20% and βBβ decreases his efficiency by 40%, then the time required to complete the work remains unchanged. Find the ratio of efficiencies of βAβ and βBβ, respectively.Solution
Let the efficiency of βAβ and βBβ be βxβ units/day and βyβ units/day, respectively. So, total work = {(x + y) Γ 18} units After change in efficiencies, Also, total work = (1.2x + 0.6y) Γ 18 So,
1.2x + 0.6y = x + y Or,
0.2x = 0.4y Or,
x : y = 2 : 1 So, ratio of efficiency of βAβ and βBβ = 2 : 1
The monocotyledonous plants can be distinguished from dicotyledonous plants by:
Which of the following is not a stem modification?
Which of the following cucurbits is richest in iron content?
Pea, gulmohur, bean, Cassia have ___ type of symmetry and hance they are ____ flowers.
The organelle responsible for protein synthesis in plant cells is the:Β
When the leaflets are joined together at a common point at the petiole, the type of leaf is
Photosynthesis occurs in which cell organelle of the plant?Β
In monocotyledonous seeds the outer covering of endosperm separates the embryo by a proteinous layer called as
Pungency in radish is due to the presence of
Which of these green manuring crop is stem nodulating?