18 workers can complete 9 tasks in 24 hours. Find the time
required by 12 workers to finish 15 tasks.Solution
ATQ,
Let the efficiency of each worker be 'x' tasks per hour
Let the required time be 't' hours
Therefore, (18x × 24) / 9 = (12x × t) / 15
Or, t = (18x × 24 × 15) / (12x × 9) = 60
Required time = 60 hours
Choose the option that is the passive form of the sentence.
They need 104 more runs to win the match.
Â
Select the correct Active/Passive form of the given sentence-
Where was the game being played ?
Choose the option that is the passive form of the sentence.
The first settlers displaced the original inhabitants.
The following sentences describe the process of baking a cake in a microwave. Identify the step which is NOT expressed in passive voice.
Select the correct passive form of the given sentence.
She can do only one thing at a time.
Select the option that expresses the following sentence in passive voice:
They will complete the project by next week.
Select the correct passive form of the given sentence.
Hasn’t India established the air travel bridge to the Maldives?
Given below is a word, followed by three sentences that consist of that word. Identify the sentences(s) that best express( es) the meaning of the word....
Select the correct active voice of the given sentence.
They were questioned by the immigration officer.
 Groups of four words are given. In each group one word is rightly spelt. Find the rightly spelt word.
 (a)  Translucent      (b)  ...