Question
18 workers can complete 9 tasks in 24 hours. Find the time
required by 12 workers to finish 15 tasks.Solution
ATQ,
Let the efficiency of each worker be 'x' tasks per hour
Let the required time be 't' hours
Therefore, (18x × 24) / 9 = (12x × t) / 15
Or, t = (18x × 24 × 15) / (12x × 9) = 60
Required time = 60 hours
Under GST, the tax levied on intra-state supply of goods is shared between:
For intra-State sales, the GST is divided between the Centre and the State in the ratio?
A ________ is not an actual contract but it resembles a contract. In other words, it is a contract in which there is no intention on part of either part...
In monetary policy operations, the Reverse Repo Rate refers to:
The 'Payback Period' method of capital budgeting evaluates a project based on:
The level at which a fresh order should be placed for the replenishment of the stock is known as ______.
The first auditor of a company (other than government company) is appointed by the ______ within ______ of registration of the company by passing a vali...
Which one of the following is exempt income?
An audit firm is appointed to audit a client that has recently engaged in a major merger with a company where the audit firm’s senior partner holds sh...