Question
A alone can complete a work in 16 days and B alone in 12
days. Starting with A, they work on alternate days. In how many days, total work will be completed?Solution
Assume total work = LCM(16,12) = 48units A’s 1 day work = 48/16 = 3units B’s 1 day work = 48/12 = 4 units So if they work on alternate days, total work in 2 days = 3 + 4 = 7 units Hence Work in 2 days = 7 units -----(1) Multiplying equation (1) by 6, we will get, Work done in 12 days = 42 units Remaining work =48-42 = 6 unit Work in 13th day by A = 3 units So total work done in 13 days = 42 + 3 = 45 units now remaining work = 3unit Now, in next day, B can do 4 units work but remaining work is only (48 - 45) = 3. Hence B will take ¾ day to complete the remainig work 3 unit total days = 13+3/4 So Total days = 13
days
23 45 89 155 ? 353
580 557 528 497 ? 419
(14.073)² + (32.103)² + (43.9653)² + (52.983)² + ? = (102.45)² + (98.007)²
Complete the series choosing the missing number.
110, 99, 86, ___, 54, 35.
The question below is based on the given series I. The series I satisfy a certain pattern, follow the same pattern in series II and answer the questions...
What will come in place of the question mark (?) in the following series?
17, 81, 131, 169, 197, ?
226 231 466 ? 5606 28031
10, 10, 15, 30, 75, ?
What will come in place of the question mark (?) in the following series?
72, 78, 90, ?, 132, 162
What will come in the place of questions (?) mark in the following questions.
1204, 1218, ? , 1267, 1302, 1344