Question
A alone can complete a work in 16 days and B alone in 12
days. Starting with A, they work on alternate days. In how many days, total work will be completed?Solution
Assume total work = LCM(16,12) = 48units A’s 1 day work = 48/16 = 3units B’s 1 day work = 48/12 = 4 units So if they work on alternate days, total work in 2 days = 3 + 4 = 7 units Hence Work in 2 days = 7 units -----(1) Multiplying equation (1) by 6, we will get, Work done in 12 days = 42 units Remaining work =48-42 = 6 unit Work in 13th day by A = 3 units  So total work done in 13 days = 42 + 3 = 45 units now remaining work = 3unit Now, in next day, B can do 4 units work but remaining work is only (48 - 45) = 3. Hence B will take ¾ day to complete the remainig work 3 unit total days = 13+3/4               So Total days = 13
 days
A series of still pictures on one roll is called:
The primary raw material used for commercial manufacturing of Muriate of Potash fertilizer
A trisomy can be represented by
The bulk density of soil was 1.40 Mg/m3 and particle density was 2.70 Mg/m3. Calculate pore space in soil.
Food Analysts have a major role to play in ______ of food samples in the food laboratories
Based on the manner of connection with tractors, which of the following classification is NOT true for a plough?
What is the harvesting stage of Arecanut?
The correct order of boiling point of primary (1 Ëš ), secondary (2 Ëš ) and tertiary (3 Ëš ) alcohols is
Fertilizer insoluble in water and citric acid
Given below are two statements
Statement I: A surface irrigation event is composed of four phases namely, advance phase. storage phase, deple...