Question
A, B, and C together can do a project in (64/7) days. B and C together need (96/9) days, and C alone completes half in 8 days. Find A : B (efficiency).
More Time and work Questions
- 40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are nee...
- Ritu completes 50% of a project in 25 days, while Sheetal completes 40% in 32 days. Ritu works for 30 days and then stops. Find the time Sheetal needs to f...
- 24 men can complete _______% of the whole work in 12 days working 10 hours in a day. 30 men working 8 hours in a daycan complete 30% of the whole work in _...
- 'N' men can complete a work together in 25 days. All of them started the work together, but each day, two men left the work. The total time taken to comple...
- Aman can complete a task in 24 days, while Bhavna can finish the same task in 40 days. How long will it take for Chetan to finish the task if his efficienc...
- Eight men and five boys together earn ₹3,240 in 6 days. Meanwhile, three men and two boys working together take 12 days to earn ₹2,484. How many days will ...
- A is four times as efficient as B and can finish a piece of work in 33 days less than B. B can finish this work in how many days?
- Ravi and Sanjay take 54 days to build a fence. When they work along with Rahul, the work gets done in 36 days. Find the time Rahul alone would take to buil...
- If Riya takes three times the time that Mahi takes or four times the time that Neha takes to finish a task, and all three working together can complete it ...
- A and B together can complete a work in 10 days. B and C together can do it in 12 days, and A and C together can do it in 15 days. In how many days will al...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)