Question
‘P’ and ‘Q’ can complete a task together in 24 days. If ‘P’ alone can do it in 40 days, find the number of days ‘Q’ alone will take to finish the task.
More Time and work Questions
- If a group of 15 boys and 10 girls can finish a task in 36 days, and a team of 5 girls alone can complete the same task in 72 days, how long will it take f...
- A and B together can complete a work in 12 days, and B alone can complete it in 20 days. How many days will A take to complete the work alone?
- 6 women and 4 children can complete a piece of work in 12 days. If 3 more women join them, they can finish 3/5 of the work in 6 days. Find the time taken b...
- 20 men can finish a work in 220 days, but at the end of 90 days, 20 additional men are employed. In how many more days will the work be completed?
- ‘A’ and ‘B’ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after ‘x’ days ‘A’ left the work and the r...
- The ratio of time taken by P, Q and R to complete work alone is 4:5:2 respectively. If all three together complete the work in 8 days, then find in how man...
- 10 man can make a wall in 8 days. How many men required to complete the same work in half days ?
- A can complete a work in 12 days and B can complete the same work in 18 days. They work together for 4 days, after which A leaves. In how many more days wi...
- A woman is one-third as efficient as a man. How much time will 9 women take to complete a job that is 75% of the work done by 10 men in 12 days?
- A and B can complete a task together in 8 days, while B alone takes 16 days to finish it. A began working alone and left after ‘x’ days, after which B comp...