      A and B can do a piece of work in 12 days and 18 days,

      respectively. They start working together, and after 4 days, A leaves the work. How many more days will B take to complete the remaining work?
      A 5 days Correct Answer Incorrect Answer
      B 6 days Correct Answer Incorrect Answer
      C 7 days Correct Answer Incorrect Answer
      D 8 days Correct Answer Incorrect Answer

      Solution

      Rate of A = 1/12 per day, Rate of B = 1/18 per day. In 4 days, A and B together complete: (1/12 + 1/18) Γ— 4 = (3 + 2) / 36 Γ— 4 = 20 / 36 = 5/9 of the work. Remaining work = 1 - 5/9 = 4/9. B's rate is 1/18 per day. B will take: (4/9) / (1/18) = 4/9 Γ— 18 = 8 days. Correct answer: d. 8 days