Question
X can do a piece of work in 30 days. He worked at it for
5 days and then Y finished it in 20 days. In how many days can X and Y together finish the work?Solution
X’s five day work = 5/30 = 1/6 Remaining work = 1 – 1/6 = 5/6 This work was done by Y in 20 days. Y does 5/6th of the work in 20 days, he will finish the work in 20 × 6/5 = 24 days. X & Y together would take 1/24 + 1/24 = 2/24 = 1/12 i.e. 12 days to complete the work.
According to the 2011 census, which of the following states of India is the lowest sex ratio?
Which organization was established in response to the December 2004 Indian Ocean tsunami?
What is the name of antibiotic containing chlorine which is produced by soil containing microorganisms and is effective for the treatment of typhoid fever?
In India, cricket was brought by whom?
The request/reply protocol for exchanges on the internet network is called:
Consider the following statement about Center of Excellence (CoE) named ATMAN:
1. Full form of the ATMAN is Advanced Technologies for Monitoring ...
The crops sown during the winter season are called _____________ crops.
'Hardaul Katha' are folk songs typical to __________ which spreads over Uttar Pradesh and Madhya Pradesh
PM Mitra Mega Textile Park will be set up in how many states?
Who among the following was a saint from Maharashtra?