X can do a piece of work in 30 days. He worked at it for
5 days and then Y finished it in 20 days. In how many days can X and Y together finish the work?Solution
X’s five day work = 5/30 = 1/6 Remaining work = 1 – 1/6 = 5/6 This work was done by Y in 20 days. Y does 5/6th of the work in 20 days, he will finish the work in 20 × 6/5 = 24 days. X & Y together would take 1/24 + 1/24 = 2/24 = 1/12 i.e. 12 days to complete the work.
Which of the following act is not administered by RBI?
What does R stand for in term LIBOR?
........................................is a contractual agreement made between two parties, in which one party agrees to pay for potential losses or da...
What is the limit on the amount of money for trade related transactions under RDA?
What is the budget allocation for the National Commission for Safai Karamcharis (NCSK) for the year 2025-26?
In which market are funds typically transacted on an overnight basis?
What is the main function of Central Depository Services (India) Ltd (CDSL)?
Which of the following is true about the Debit Card of the Banks?
I. By Automated Teller Machine customers can deposit or withdraw money from the...
Goods and Services Tax in India is a tax based on which criteria?
Sale of Rs.50,000 to ‘A’ was entered as a sale to ‘B’. This is an example of –Â