X can do a piece of work in 30 days. He worked at it for
5 days and then Y finished it in 20 days. In how many days can X and Y together finish the work?Solution
X’s five day work = 5/30 = 1/6 Remaining work = 1 – 1/6 = 5/6 This work was done by Y in 20 days. Y does 5/6th of the work in 20 days, he will finish the work in 20 × 6/5 = 24 days. X & Y together would take 1/24 + 1/24 = 2/24 = 1/12 i.e. 12 days to complete the work.
Gol Gumbaz is the mausoleum of the king Mohammed Adil Shah. It is a part of_________.
To which of the state does Sattriya classical dance belong?
Which of the following initiatives for the MSME sector was launched before 2020?
What was the reason for awarding the Nobel Prize to Guglielmo Marconi and Karl Ferdinand Braun in 1909?

Which West African countries recently declared its decision to withdraw from the Economic Community of West African States (ECOWAS)?
Which countries were involved in the falklands war 1982?
The Finance Ministry made it mandatory for all government departments to make payments above Rs ____ through e-Payment facility and not cash?
What numerical value represents the escape velocity?Â
When was Vikram award introduced in Madhya Pradesh ?