Question
X can do a piece of work in 30 days. He worked at it for 5 days and then Y finished it in 20 days. In how many days can X and Y together finish the work?
More Time and work Questions
- Mike and Jenny alone can complete a task in 24 days and 40 days respectively. They aim to finish the work in 'd' days. What percentage increase in Jenny's ...
- X, Y and E can do piece of work in 24, 30 and 40 days respectively. All three began to work together but X and Y left 6 and 8 days respectively before comp...
- A can complete a work in 12 days and B in 18 days. They work together for 6 days, then B leaves. How many total days to finish the work?
- A can complete a piece of work in 21 days. A starts the work alone. After 9 days, B joins A, and together they complete the remaining work in 5 days. Find ...
- A can complete 25% of work in five days. And this takes four days more than B to complete the whole work. They started the work together but after X days A...
- R and S take 10 days and 15 days respectively to complete a task alone. If they alternate work every day starting with R, how much time will it take to fin...
- 'A' and 'B' can complete a piece of work in 10 days, 'B' and 'C' can complete the work in 16 days, and 'A' and 'C' can complete the work in 20 days. Find t...
- There is enough food in a camp to last for 40 days if each of the 60 soldiers present at the camp eat 3 times a day. After 10 days, 10 soldiers left the ca...
- A and B can do a job in 20 days and 30 days, respectively. A and B work together for 5 days, and then A leaves. After how many more days will B complete th...
- A and B can finish a job in 10 and 15 days respectively. They start together, but after 2 days A leaves. How many more days will B take to complete the res...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt