Question
A, B and C can complete a work in 2 days. If A alone can
complete the same work in 6 days and B in 4 days, how long will it take for C to finish the work alone?Solution
ATQ: A + B + C = 2 A = 6 B = 4 Total work = 12 (LCM of 2, 6 and 4) A + B + C = 12/2 = 6 A = 12/6 = 2 B = 12/4 = 3 efficiency of C = (6 - (2 + 3)) = 1 Therefore, c will take 12/1 = 12 days
Approximately what is the Coefficient of Variation of first 50 natural numbers ?
Which of the following is a possible change in total revenue that occurs if you increase the price of a good with unit elasticity?
Which of the following best explains why the J-curve effect occurs?
The velocity of money is
If the money supply grows 5 per cent, and real output grows 2 per cent, prices should rise by
Which method is used by Hicks to eliminate the income effect when price of a product is changed
Commodity X and Y have an equal price elasticity of supply. The supply of X rises from 400 units to 500 units due to a 20 percent rise in its price. Cal...
What is the probability of getting the sum as a prime number if two dice are thrown?
What is the terms of trade formula?
What is the Slope of the Straight line PPC curve between cloth and wheat?