Question
A, B and C can complete a work in 2 days. If A alone can
complete the same work in 6 days and B in 4 days, how long will it take for C to finish the work alone?Solution
ATQ: A + B + C = 2 A = 6 B = 4 Total work = 12 (LCM of 2, 6 and 4) A + B + C = 12/2 = 6 A = 12/6 = 2 B = 12/4 = 3 efficiency of C = (6 - (2 + 3)) = 1 Therefore, c will take 12/1 = 12 days
Which of the following statements is/are correct?
Statement 1: Major Radhika Sen received the U.N. Military Gender Advocate of the Year Award f...
Indian Institute of Technology-Bombay has tied up with which company to launch a 'Bharat GPT' programme that will be launching products and services i...
State Bank of India  has raised ________ in debt capital by issuing Tier-II bonds at a coupon rate of 7.81 per cent in order to meet the regulatory c...
Which Indian institution ranked highest in the QS World University Rankings 2026?
How has the sovereign gold bonds (SGBs) scheme impacted India's gold import bill in the financial year 2023-24?
According to the UDISE+ report 2023-24, what is the total student enrolment in India for the year 2023-24?
What is the name of the multinational peacekeeping exercise held in Mongolia in which the Indian Army participated in June 2025?
What is the primary goal of the Election Commission of India's "Mission 414" initiative in Himachal Pradesh?
World Zoonoses Day 2025 commemorates which historical medical achievement?
Exercise Sangam, a joint Naval Special Forces exercise between India and which country?