πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A can complete a work in 10 days and B can complete it

      in 15 days. They work together for 4 days, then A leaves. In how many days will B finish the remaining work alone?
      A 12 days Correct Answer Incorrect Answer
      B 8 days Correct Answer Incorrect Answer
      C 5 days Correct Answer Incorrect Answer
      D 10 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Work/day together = 1/10 + 1/15 = (3+2)/30 = 1/6 Work done in 4 days = 4Γ—(1/6) = 2/3 Remaining work = 1 βˆ’ 2/3 = 1/3 B’s work/day = 1/15 Time = (1/3) Γ· (1/15) = (1/3)Γ—15 = 5 days

      Practice Next
      ask-question