    Question

    A can complete a work in 10 days and B can complete it

    in 15 days. They work together for 4 days, then A leaves. In how many days will B finish the remaining work alone?
    A 12 days Correct Answer Incorrect Answer
    B 8 days Correct Answer Incorrect Answer
    C 5 days Correct Answer Incorrect Answer
    D 10 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ, Work/day together = 1/10 + 1/15 = (3+2)/30 = 1/6 Work done in 4 days = 4×(1/6) = 2/3 Remaining work = 1 − 2/3 = 1/3 B’s work/day = 1/15 Time = (1/3) ÷ (1/15) = (1/3)×15 = 5 days