Question
Ram can do a piece of work in 50 days. He alone worked at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, they will complete the whole work, working together?
More Time and work Questions
- Karan, Arjun and Krunal alone can complete a work in 30, 45 and 36 days respectively. All of them started working together but after 3 days from start Kara...
- Virat can do a piece of work in 26 days and Sachin can do the same work in 39 days. If Virat works for 5 days and got Rs. 3000, and the remaining work will...
- Sanya can finish a task by herself in 20 days, while when working together, Riya and Sanya can complete the same task in 10 days. Riya starts the work alon...
- Two efficient workers or three non-efficient workers can complete a certain task in 20 days. If each efficient worker improves their efficiency by 33(1/3)%...
- A can plough a field alone in 12 days and B alone can do it in 18 days. They work together for 4 days and then B alone finishes the remaining work. In how ...
- ‘A’ can complete a work in 15 days and is 50% more efficient than ‘B’. ‘A’ and ‘B’ start working together and ‘A’ leaves after 8 days. The rest of the work...
- 6 women and 4 children can complete a piece of work in 12 days. If 3 more women join them, they can finish 3/5 of the work in 6 days. Find the time taken b...
- ‘A’ and ‘B’ can complete a certain work in 10 days and 15 days, respectively. They started working together and worked till completion of the work for whic...
- X can do a piece of work in 25 days. He worked at it for 5 days and then Y finished it in 24 days. In how many days can X and Y together finish the work?
- 'Aman' and 'Bhanu' together can complete a work in 7.2 days. Both of them started the work but 'Bhanu' left the work after 3 days and remaining work was co...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)