Question
P can do a piece of work in 30 days. Q do the same work
in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for some days and handed it again to P and R 6 days before completing the work. For how many days did Q work?ÂSolution
L.C.M of 30, 40 and 35 days = 840 days P can do 840/30 = 28 units/day Q can do 840/40 = 21 units/day R can do 840/35 = 24 units/day Now, in (4 + 6) days (P + R) can do = 10 × 52 = 520 units Therefore, Remaining unit work done by Q = 840 – 520 = 320 Therefore, Q’s work for (320/21) = 15(5/12)days Â
Non programmed decisions are most likely to be made by _________
Which of the following types of decision is needed for unique problems?
With the expected downturn in the economy, a bank anticipates its bad loans to increase by the end of the year. The bank decides to create extra provisi...
A manager's freedom to make totally rational decisions is restricted by internal and external environmental factors and by the manager's own characteris...
Which of the following is a decisional role that a manager usually performs as per Henry Mintzberg?
Which of the following is not true regarding emotional decision making?
Which of the following types of managers improve decision making skills in their team members?
The NABARD Chairman called a meeting of all the Managers and asked them to give their ideas to a stated problem. The Chairman listened to all the idea ...
Discussing a problem face to face with open mind by a group of selected persons is known as _________
Which of the following is an intuitive decision?