Question

5 Pandavas can do a work in 18 days, 4 Kauravas can do the same work in 30 days. Now, in how many total days the total work be finished if 1 Panadva and 1 Kaurava working together?

A 522/5 days
B 254/5 days
C 360/7 days
D 430/7 days
E None of these