Question
Karan can do 80% works in 40 days. Remaining work completed by Karan and Arjun in 6 days. In how many total days the total work is finish if Arjun work alone?
More Time and work Questions
- The team of A B and C was supposed to complete a piece of work. Working alone, A could have completed the same work in 190 hours. B could have completed th...
- A work can be completed by ‘A’ and ‘B’, alone in 12 days and 18 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- Person A can complete a certain task in 20 days, while person B can finish the same task in x days. Together, they can complete the task in 12 days. Determ...
- A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 25 days. Find the time taken by B to complete 20% of...
- 'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' and '...
- "Akash and Bittu can individually complete a task in 40 days and 50 days, respectively. They start working together, and after 10 days, Chinky joins them. ...
- 2 men and 4 boys can together complete a work in 6 days. 3 men and 1 boy can together complete the same work in 5 days. Find the time taken by 10 boys toge...
- Pooja is twice as efficient as Nita and four times as efficient as Kavya. If Nita takes 30 days to finish some work, then find the time taken by Pooja and ...
- Anand is capable of finishing a task in 36 days when working solo. Akash, being 40% more efficient than Anand, can accomplish tasks quicker. Calculate how ...
- If 12 men can build a wall in 15 days, how many men are required to build the same wall in 10 days?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)
Karan – 40 × 5/4 = 50 Karan + Arjun – 6 × 5/1 = 30
Arjun = 150/(5-3) = 75 days