Question
If 12 men can build a wall in 15 days, how many men are required to build the same wall in 10 days?
More Time and work Questions
- A pipe can fill a tank in 20 hours, and B pipe can drain a tank in 15 hours. If a system of N pipes (fill pipes and drain pipes put together) can fill the ...
- Ravi can finish 50% of a job in 20 days, while Ramesh can finish 40% of the same job in 32 days. Both start working together, but Ravi leaves after some ti...
- 6 interns together do as much work as a regular employee. If 36 interns finish 90 tasks in 3 days, how many regular employees are required to do 90 tasks i...
- A buffalo alone can plough field ‘A’ in 10 days. A Bull alone can plough the field ‘A’ in 16 days. Find the number of days taken by 1 bulls and 3 buffalo t...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 16 days. 'A' started the work alone and worked on...
- Ajay and Vijay can finish a task in 9 days working together. Charu, who is twice as efficient as Vijay, can complete the task alone in 18 days. If Ajay and...
- ‘A’ can finish a project in 40 days, whereas ‘B’ finishes 50% of the project in 12 days less than ‘A’. How many days will it take both ‘A’ and ‘B’ to compl...
- A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days will ...
- Ratio of the work done by P, Q and R in one day is 6:4:7 respectively. They all together can complete the work in 45 days. Q and R worked on it for 27 days...
- Anil and Ashish receive Rs.2000 for work of 10 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt