Question
'P' and 'Q' can finish a piece of
work in 45 days and 90 days, respectively. 'P' starts working alone, and 'Q' joins after 'r' days, ensuring that the entire work is completed in '2r' days. Find the value of 'r'.Solution
ATQ,
Let the total work be 90 units. {LCM of 45 and 90} Efficiency of 'E' = 90 ÷ 45 = 2 units/day Efficiency of 'F' = 90÷ 90 = 1 units/day So, 2r + 2r + 1r = 90 Or, 5r = 90 Therefore, r = 18
Consider the following statements about National Geoscience Data Repository (NGDR) Portal:
1. Union Ministry of Mines launch the NGDR...
What is the targeted number of educators to be empowered through AI Productivity Labs under the IndiaAI and Microsoft partnership?
How many wickets did Amit Mishra take in his Test career?
Recently which international organisation has approved a USD 96.3 million (about Rs 770 crore) loan to fund safe drinking water and sanitation project ...
Who inaugurated the 'Garia and Borsho Boron Utsav' 2025 in Agartala?
Which aerospace company has entered into an agreement with Satellogic Inc for establishing and developing local space technology capabilities & to integ...
"Har Khet Ko Paani" is the motto of which of the following Schemes?
Consider the following statements about UNESCO's Prix Versailles award:
1. Recently, IGI Airport has won this award.
2. �...
______ is the structural and functional unit of kidney.
According to the survey by credit rating agency S&P Global, Purchasing Managers' Index (PMI) declined marginally to____ in May from its 13-year high o...