Question
'P' and 'Q' can finish a piece of work in 45 days and 90 days, respectively. 'P' starts working alone, and 'Q' joins after 'r' days, ensuring that the entire work is completed in '2r' days. Find the value of 'r'.
More Time and work Questions
- ‘X’ can finish 50% of a job in 8 days. ‘Y’ takes 8 days more than ‘X’ to complete the entire work, and Y is 20% more efficient than ‘Z’. ‘X’ starts the tas...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
- Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by ...
- ‘P’ can complete a project in 12 days. ‘Q’ is 40% less efficient than ‘P’. Working together, ‘P’, ‘Q’ and ‘R’ can finish the job in 5 days. In how many day...
- ‘M’ and ‘N’ can do a piece of work in 9 days and 18 days, respectively. ‘M’ started working alone and was replaced by ‘N’ after 3 days. In how many days ca...
- A is four times as efficient as B and can finish a piece of work in 33 days less than B. B can finish this work in how many days?
- A pipe can fill a tank in 12 hours, while a second pipe can empty it in 18 hours. If both pipes are opened at the same time, how long will it take to fill ...
- Person A can complete a certain task in 20 days, while person B can finish the same task in x days. Together, they can complete the task in 12 days. Determ...
- A task can be finished by 'P' and 'Q' alone in 10 days and 5 days, respectively. 'P' and 'Q' started the task together and after 3 days, 'P' was replaced b...
- Komal and Seema individually can complete a task in ‘3a’ hours and ‘5a’ hours respectively. If they together can complete (4/5)th of the work in 3 hours, t...