Question

X can finish a task in 20 days, while Y can do it in 25 days. If Z needs 1.2 times the time taken by X and Y together, find the number of days Z will take to complete the same task.

A 17.33 days
B 27.27 days
C 20.20 days
D 13.33 days
Practice Next

More Time and work Questions

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)