Question
L completes a project in 18 days, and K completes the same
in 27 days. If J alone takes 1.3 times the time taken by L and K working together, find the number of days J will take.Solution
ATQ,
Time taken by L and K together to complete the work = (18 Ă— 27)/ (18 + 27) = 10.8 days
Time taken by J alone to complete the work = 1.3 Ă— 10.8 = 14.04 days
The disorder of carrot that occurs due to undecomposed manure and hard soil pan
 Every year to raise awareness about the importance of soil quality for food security, healthy ecosystems, and human well-being, World soil day is cele...
The acidic soils can be reclaimed by the application of ____
Soil texture is determined most commonly by which method?Â
Which of the following is the progeny of breeder seed and is responsible for producing certified seed?
Which soil type covers the maximum area in India?
Soil health card with the tagline “Swasth Dharaa, Khet Haraa” was launched on ____.
The soils of grassland ecosystems, characterized by a thick, dark surface horizon comes under which soil order?
The term “operational holding” refers to
Disorders like Hollow Stem of Cauliflower; Browning of Cauliflower ; Top sickness of Tobacco is caused due to the deficiency ofÂ