πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      L completes a project in 18 days, and K completes the same

      in 27 days. If J alone takes 1.3 times the time taken by L and K working together, find the number of days J will take.
      A 14.04 days Correct Answer Incorrect Answer
      B 26.04 days Correct Answer Incorrect Answer
      C 20.02 days Correct Answer Incorrect Answer
      D 19.03 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Time taken by L and K together to complete the work = (18 Γ— 27)/ (18 + 27) = 10.8 days

      Time taken by J alone to complete the work = 1.3 Γ— 10.8 = 14.04 days

      Practice Next
      ask-question