Question
L completes a project in 18 days, and K completes the same
in 27 days. If J alone takes 1.3 times the time taken by L and K working together, find the number of days J will take.Solution
ATQ,
Time taken by L and K together to complete the work = (18 × 27)/ (18 + 27) = 10.8 days
Time taken by J alone to complete the work = 1.3 × 10.8 = 14.04 days
Change the question mark with the option that follows the applied logic in the first pair.
J : P :: M : ??
Read the given statement and conclusions carefully and decide which of the conclusions logically follow(s) from the statement.
Statement:
<...How many triangles are there in the given figure?
If the two signs, '× and ÷' are interchanged, which of the following equations will be correct?
Six boxes, labelled A, B, C, D, E and F, are arranged vertically from top to bottom. The top position is considered as the 1st position, whereas the bot...
Identify the figure that completes the pattern (rotation is NOT allowed).
Select the figure from among the given options that can replace the question mark (?) in the following series.Â
Select the option that represents the correct order of the given words as they would appear in an English dictionary.
1. Circulate
2. Circ...
Select the correct option that indicates the arrangement of the given words in the order in which they appear in an English dictionary.
1. Realis...
In a certain code language, ‘ANCIENT’ is written as ‘EPCIVPG’ and ‘ADVANCE’ is written as ‘XFCAGEP’. How will ‘ABILITY’ be written i...