Question
A, B, C and D are four workers. The ratio of efficiency of C and D is 3 : 4 and that of A and B is 1 : 2. Find the time taken by D to finish the job alone.
A, B, C and D are four workers. The ratio of efficiency of C and D is 3 : 4 and that of A and B is 1 : 2. Find the time taken by D to finish the job alone.
I. A and D work together and finish the job in 12 days.
II. A, B and C together complete the job in 10 days.
III. B and D together finish the job in 10 days.
More Time and work Questions
- A and B can complete a task together in 24 days, while B alone takes 48 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- Rohan can finish a task alone in 24 days. Shreya can do 50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% of ...
- P, Q, and R can complete a work in 12 days. 15 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and ...
- A and B can finish a job in 10 and 15 days respectively. They start together, but after 2 days A leaves. How many more days will B take to complete the res...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 10 t...
- A and B can complete a work together in 18 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x...
- ‘M’ and ‘N’ together can do a work in 20 days. If ‘M’ increases his efficiency by 25% while ‘N’ decreases his efficiency by 50%, then the time taken to com...
- Ram and Shyam are partners in completing a project. Ram can finish the project in 42 days, while Shyam can complete it in 54 days. Both began the project t...
- P can complete a piece of work in 15 days. Q in 20 days and R in 30 days. P and R worked together for three days and then P was replaced by Q. In how many ...
- A and B can complete a work together in 32 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alone in 6...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)