ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    Individually, X, Y and Z can finish a job in 15 days, 20

    days, and 24 days respectively. How many days will they take to complete the job working together?
    A 6(6/19) days Correct Answer Incorrect Answer
    B 2(5/19) days Correct Answer Incorrect Answer
    C 3(7/19) days Correct Answer Incorrect Answer
    D 4(1/19) days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let the total work be 120 units (LCM of 15, 20 and 24)

    Efficiency of 'X' = (120 ├╖ 15) = 8 units/day

    Efficiency of 'Y' = (120 ├╖ 20) = 6 units/day

    Efficiency of 'Z' = (120 ├╖ 24) = 5 units/day

    Required time = 120 ├╖ (8 + 6 + 5) = (120 ├╖ 19) = 6(6/19) days

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question