Question
How can we determine the value of x, given that (x+8) workers, working 9 hours a day, can finish 60% of a task in 12 days, and (x+2) workers, working 3 hours a day, can complete the remaining work in 32 days?
More Time and work Questions
- 25 men can complete a piece of work in 13 days. One man starts the work and after every day one more man joins the work and this continues till the work is...
- A work can be completed by ‘A’ and ‘B’, alone in 18 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- Amit and Ankit can complete a job in 60 days. Working together with Sumit, they can finish it in 40 days. How many days would Sumit alone take to complete ...
- A man can complete a task in 20 days, a woman can finish it in 30 days, and a boy can do the same task in 60 days. To complete the task in just 3 days, how...
- Ravi and Sita together can complete a piece of work in 150 days and 3 minutes, while Sita and Ramesh together can complete the same work in 90 days and 2.5...
- ‘P’ is 20% more efficient than ‘Q’. ‘P’ can do a piece of work in 15 days. They begin the work together, but ‘Q’ leaves after 6 days. The rest of the work ...
- A can finish a work in 18 days and B can finish it in 24 days. They work together for 6 days, then A leaves. In how many more days will B finish the remain...
- A can complete 1/4th of a work in 5 days while B can complete 1/5th of the same work in 6 days. In how many days both of them together can complete the who...
- 12Men and 12women can complete a piece of work in 9 days. 6 men and 15 women can complete the same work in 12 days. How long (in days) would it take 9 wome...
- Amit can do certain work alone in 'w' days. Arjit can do the same work alone in (w + 12) days.Gaurav started working and did (1/2) the work at the efficien...