Question
'A' alone can do some work in 20 days. 'B' is 60% more
efficient than 'A'. 'A' worked alone for 12 days and left. How much time (in days) does 'B' need to finish the remaining work?Solution
Let the efficiency of 'A' be x units/day.
So, efficiency of 'B' = 1.6x units/day.
Total work = 20 × x = 20x units.
Work done by 'A' in twelve days = 12 × x = 12x units.
Remaining work = 20x − 12x = 8x units.
Time taken by 'B' to finish the remaining work = ({8x/1.6x} = 5) days.
When was the World Bank established?
Which bank has become the first to officially introduce the Mahila Samman Savings Certificate (MSSC) scheme?Â
Where did the 36th National Games take place in September – October 2022?
Which type of banks are allowed to participate in government related business?
Which one of the following is provided under the Third Schedule of the Factories Act, 1948?
Which of the following personalities was conferred with the ‘Padma Vibhushan’ award?Â
Business, commerce and movement within India are described as part of the Constitution?
______ drains into Arabian sea.
In a volleyball game, each team comprise of how many players?
 To reduce a bank’s risks on confirmations and negotiations of irrevocable letters is called?