ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    'A' alone can do some work in 20 days. 'B' is 60% more

    efficient than 'A'. 'A' worked alone for 12 days and left. How much time (in days) does 'B' need to finish the remaining work?
    A 5 days Correct Answer Incorrect Answer
    B 6 days Correct Answer Incorrect Answer
    C 4 days Correct Answer Incorrect Answer
    D 9 days Correct Answer Incorrect Answer

    Solution

    Let the efficiency of 'A' be x units/day.
    So, efficiency of 'B' = 1.6x units/day.
    Total work = 20 ├Ч x = 20x units.
    Work done by 'A' in twelve days = 12 ├Ч x = 12x units.
    Remaining work = 20x тИТ 12x = 8x units.
    Time taken by 'B' to finish the remaining work = ({8x/1.6x} = 5) days.

    Practice Next
    More Time and work Questions
    ask-question