Question
Sam and John can complete a piece of work in 8 days and
12 days respectively. They work together but after 2 days, Sam leaves. John finishes the remaining work alone. Find out the fraction of the work done by John.Solution
ATQ, Let the total amount of work be 24units (LCM of 8 and 12) Efficiency of Sam = 24/8 = 3 units/day Efficiency of John = 24/12 = 2 units/day Work done together in 2 days = (3+2) × 2 = 10 units Remaining work = 24-10 = 14 units, completed by John alone. Units of work done by John = 14+(2×2) = 14 +4 = 18 units Part of work done by John = 18/24 = 3/4
As per Census 2011, which among the following states has the highest sex ratio (number of females per 1000 males) in India?
Which Veda contains information about the most ancient Vedic age culture?
Which company recently announced plans to establish an AI Cluster at Gujarat International Finance Tec-City (GIFT City) in Gandhinagar, Gujarat?
According to Jain texts, which Jain Tirthankar performed penance in Haridwar?
Who had won the Wildlife Conservation Award 2023?
If the court finds that a person is holding office but is not legally entitled to hold that office, the judiciary restricts that person from a acting as...
Who has won the Singapore literature award for the English Fiction?
The BioE3 policy emphasizes the development of which kind of economy?
Which company has launched Team India's jersey for the upcoming ICC World Cup 2023?
Union Home Minister Amit Shah launched the ‘Vibrant Villages Programme’ (VVP) in April 2023 in which district of Arunachal Pradesh?