Sam and John can complete a piece of work in 8 days and
12 days respectively. They work together but after 2 days, Sam leaves. John finishes the remaining work alone. Find out the fraction of the work done by John.Solution
ATQ, Let the total amount of work be 24units (LCM of 8 and 12) Efficiency of Sam = 24/8 = 3 units/day Efficiency of John = 24/12 = 2 units/day Work done together in 2 days = (3+2) × 2 = 10 units Remaining work = 24-10 = 14 units, completed by John alone. Units of work done by John = 14+(2×2) = 14 +4 = 18 units Part of work done by John = 18/24 = 3/4
RBI has released a list of NBFCs placed under the upper layer under the scale based regulations.With respect to the information provided, which of the f...
According to the World Health Organization, what was the approximate number of global deaths by suicide in the year 2021?
Which country topped the World Happiness Report 2025 for the eighth consecutive year?
What is the total approved outlay of the Research Development and Innovation (RDI) scheme aimed at promoting private sector R&D?
Which Indian Self-Help Group won the Equator Initiative Award 2025 by UNDP?
Under PM GatiShakti, how many aspirational districts will initially benefit from the district master plan?
How many talukas will constitute Goa’s new third district?
The database of the NeophyteID app contains information on approximately how many invasive plant species?
Consider the following in regards to SATHEE Portal:
1) The objective of the portal is to provide quality education to every student who intends t...
Who has been roped as the New Managing Director of Delhi Metro Rail Corporation (DMRC)?