Question
Thirty men working 8 hours daily
complete a task in 16 days. If the work increases to three times the original and needs to be finished in 20 days by workers putting in 6 hours per day with a 20% increase in their efficiency, how many men are required?Solution
ATQ, Let the total work be 'W' units and eiciency of each man be 'E' units/hour Let the number of men required be 'M'. ATQ: {(30 X 16 X 8 X E)/W} = {(M X 20 X 1.2E X 6)/(3 X W)} Or, M = 80
Statement:
James Holmes, a young man with no record of violence, murdered 12 people watching Batman in a Colorado cinema. However, his lawyer is ...
Directions: In the question below, a passage is given followed by few statements. Read the passage and answer the questions that follow.
Even w...
Statement: Should national anthem be played before movies in the theater.
Arguments:
I. Yes, this is the only way to show your love fo...
Statement- “Just like your mobile number, you could soon move your account from one bank to another without having to change the account number” RBI...
Statement: Should school-going children have internet access at home?
Arguments:
I. Yes, because through the internet students can hav...
Statement: Should there be a complete ban on extracurricular activities in college.
Arguments:
I. No, there is nothing wrong in partic...
Statement: Should national anthem be played before movies in the theater.
     Arguments:
    I. Yes, th...
- Statement: The average life expectancy for the Indian population as a whole is 75 years, but children born in Bihar will live an average of 77 years, and t...
- Despite the popularity of economic liberal ideas and globalization, the increasing severity of energy and environmental problems has raised many questions ...
- To prevent the spread of any disease, it is necessary to administer medicines on time. A common fallacy among people is that medicine needs to be taken onl...