Question
Thirty men working 8 hours daily
complete a task in 16 days. If the work increases to three times the original and needs to be finished in 20 days by workers putting in 6 hours per day with a 20% increase in their efficiency, how many men are required?Solution
ATQ, Let the total work be 'W' units and eiciency of each man be 'E' units/hour Let the number of men required be 'M'. ATQ: {(30 X 16 X 8 X E)/W} = {(M X 20 X 1.2E X 6)/(3 X W)} Or, M = 80
Allan Octavian Hume, a retired English ICS officer, formed the indian National Union in ______.
Which bank has introduced, âLiberty Savings Accountâ for the Indian youth?
The judges of the Supreme Court hold office till they reach the age of _______.
How many sites were chosen from India for the 2019 UNESCO Asia-Pacific Awards for Cultural Heritage Conservation?
'Hawa Ane De' is a campaign launched by which ministry ?
Name the Sri Lankan Buddhist text that provides details of the Mauryan empire.Â
With reference to medieval Indian architecture style, what is âPietra Duraâ?
Which organization is responsible for regulating the stock market in India?
When did the Sangeet Natak Akademi adopt its Memorandum of Association?
Gangu bai Hangal and Prabha Atre were exponents of the ___________ Gharana.