Question

A task can be completed in 15 days when Akash and Bittu work together. Akash is 30% more efficient than Bittu. If both started the task separately and Akash stopped after working for 10 days, how many additional days would Bittu require to finish the remaining work?

A 12.5 days
B 11.5 days
C 18.5 days
D 16.5 days
E None of these
Practice Next