Question
A task can be finished by 'P' and 'Q' alone in 10 days
and 5 days, respectively. 'P' and 'Q' started the task together and after 3 days, 'P' was replaced by 'R'. If the entire task was completed in (20/3) days, find how many days 'R' alone would take to complete the task.Solution
ATQ,
Let the efficiency of 'R' be 'x' units/day Let total work = 30 units (LCM of 10 and 5) Efficiency of 'P' = 30/10 = 3 units/day Efficiency of 'Q' = 30/5 = 6 units/day According to the question: (3 + 6) × 3 + (6 + x) × {(20/3) − 3} = 30 Or, (11/3) × (6 + x) = 30 − 27 Or, 6 + x = 9 Or, x = 3 Number of days required by 'R' to finish the work alone = 30/3 = 10 days
The probability of selecting a rotten egg randomly from a basket of 1050 eggs is 0.36. What is the number of rotten eggs in the basket?
Ten tickets numbered 1 to 15 are placed in a box, mixed up thoroughly and then one ticket is drawn randomly. If it is known that the number on the drawn...
- Find the probability of selecting a face card from a deck of well shuffled cards.
Find the probability that a number selected at random from first hundred number is a multiple of 3 or 5?Â
A box contains (x + 3) black balls, 6 yellow balls, and 5 orange balls. If two balls are selected at random and the probability of selecting two orange ...
If a coin is tossed 10 times then what is the probability of getting three heads?
- The probability that Riya passes the test is (4/9) and the probability that Aditya fails is (1/3). If both appear for the test, find the probability that t...
The names of 15 students from section A, 10 students from section B and 15 students from section C were selected. The age of all the 40 students was dif...
A coin is tossed successively three times. Find the probability of getting exactly one tail or two tails?
What is the Probability of getting a sum of ‘9’ on rolling a dice twice?