Question
A task can be finished by 'P' and 'Q' alone in 10 days
and 5 days, respectively. 'P' and 'Q' started the task together and after 3 days, 'P' was replaced by 'R'. If the entire task was completed in (20/3) days, find how many days 'R' alone would take to complete the task.Solution
ATQ,
Let the efficiency of 'R' be 'x' units/day Let total work = 30 units (LCM of 10 and 5) Efficiency of 'P' = 30/10 = 3 units/day Efficiency of 'Q' = 30/5 = 6 units/day According to the question: (3 + 6) × 3 + (6 + x) × {(20/3) − 3} = 30 Or, (11/3) × (6 + x) = 30 − 27 Or, 6 + x = 9 Or, x = 3 Number of days required by 'R' to finish the work alone = 30/3 = 10 days
Which among following statements about Bhagoriya is/are correct?
1. Bhagoriya is a one of the major festival of tribal people
2. Bha...
The National Pension System (NPS) is regulated by which organization?
In April 2022, United India Insurance, authorised capital was raised to __________ from ₹5,000 crore.
Which ceremonial folk dance of Puducherry is related to the Hindu epic Ramayana, performed at the Villianur temple in Puducherry?
The Eastern Ghats stretch from the ____________ to the Nigiris in the south.
What is 'Green' cotton? Â
Whats Dolling point of water in ranrenhen
"My Country, My Life" is the autobiography of ____.
The Nobel Prize in Literature 2024 is associated with which country (the laureate’s nationality)?
Which West African countries recently declared its decision to withdraw from the Economic Community of West African States (ECOWAS)?