Question
'Akash', 'Bishnu', and 'Chintu' formed a partnership
with investments of Rs. 4800, Rs. 3600, and Rs. 6400, respectively, for durations of 8 months, 1 year 4 months, and 4 months. What percentage more or less is the combined profit of 'Akash' and 'Bishnu' compared to that of 'Chintu'?Solution
ATQ, Respective ratio of the profits received by ‘Akash’, ‘Bishnu’ and ‘Chintu’ = (4800 × 8):(3600 × 16):(6400 × 4) = 6:9:4 Therefore, let the profit received by ‘Akash’, ‘Bishnu’ and ‘Chintu’ be Rs. 6p, Rs. 9p and Rs. 4p, respectively So, profit received by ‘Akash’ and ‘Bishnu’, together = (6p + 9p) = Rs. 15p Required % = {(15p – 4p)/4p} × 100 = 275%
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
‘X’ and ‘Y’ can do a task together in 15 days. If ‘X’ alone takes 25 days to complete it, then how much time will ‘Y’ take to finish the...
‘P’ and ‘Q’ can complete a task together in 24 days. If ‘P’ alone can do it in 40 days, find the number of days ‘Q’ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?