Question
βAβ and βBβ can do a piece of work in 30 days
and 40 days, respectively. They started working together but βAβ left after 9 days. Find the time taken by βBβ to complete the remaining work.Solution
Let total amount of work be 120 units (LCM of 30 and 40). Efficiency of βAβ = 120/30 = 4 units/day Efficiency of βBβ = 120/40 = 3 units/day Amount of work done by βAβ and βBβ together in 9 days = (4 + 3) Γ 9 = 63 units Time taken by B to complete remaining work = {(120 β 63)/3} = 19 days
Following are the Central Federations of Trade Unions of Workers formed in India:
1. Indian National Trade Union Congress (INTUC)
2. All I...
On 8th April 1929, who among the following two revolutionists threw a bomb in the Central Legislative Assembly?
How many countries are members of FIFA? Β
Β In 2021,which financial institution entered into a collaboration with Google India Pvt Ltd (GIPL) for piloting a social impact lending programme with ...
Shiv Kumar Sharma is associated with which instrument?
On which river in India was the Somasila Dam built?
Where is the National Bureau of Agriculturally important Micro-organiom situated in Uttar Pradesh?
New British Indian army memorial commemorating the sacrifice of Indian soldiers to be built in ___?
The Supreme Court banned tiger safaris in which National Park?
Who won the Golden Lotus (Swarna Kamal) award for Best Direction for a Hindi film at the 70th National Film Awards for the year 2022?