Question
‘A’ and ‘B’ can do a piece of work in 30 days and 40 days, respectively. They started working together but ‘A’ left after 9 days. Find the time taken by ‘B’ to complete the remaining work.
More Time and work Questions
- M and N together complete a work in 10 days, while N alone does it in 16 days. If the efficiency of M to O is in the ratio 5:6, what is the ratio of effici...
- X and Y can complete a task together in 24 days, while Y alone takes 48 days to finish it. X worked alone for some days and then Y completed the rest of th...
- ‘A’ alone can do some work in 10 days. ‘B’ and ‘C’ together can do the same work in 12 days. If ‘B’ is half as efficient as ‘A’, then find the time taken b...
- A can complete a work in 12 days and B can complete the same work in 18 days. A works alone for 4 days and then B alone finishes the remaining work. In how...
- 3 workers paint 5 rooms in 8 days. How many workers are needed to paint 10 rooms in 6 days?
- A, B and C alone can complete a work in 24, 48 and 32 days respectively. All of them started working together but after 2 days from start A left the job an...
- A, B, and C can finish work in 5 days, 10 days, and 15 days, respectively, working alone. A and B work on the first day, A and C work on the second day, A ...
- The day efficiency of Rajeev is equal to the one-day efficiency of Divya and Vivek together. Divya is 25% more efficient than Vivek and starts with 20% mor...
- A can finish a piece of work in 6 days and B can finish it in 12 days. In how many days will they finish the work together?
- A alone can complete 50% of a work in 20 days while B takes 16 days more than A to complete it. If B and C together can complete the work in 24 days, then ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt