Question
If 20 men or 12 boys can complete a job in 25 days, how
long will it take for a team of 15 men and 18 boys to complete the same job? (Calculate approximate value)Solution
According to the question,
20M = 12B
Or, 5M = 3B
Therefore, (15M + 18B) = (9B + 18B) = 27B
12 boys take 25 days to complete the work
Therefore, time taken by 27 boys to complete the work = (12 × 25) / 27 = 11.11 days or 11 days
Pending investigation or inquiry, the Board may attach the bank accounts of any person associated in violation of any provisions of the Act for a maxim...
What is a reasonable time for performance of a contractÂ
Which of the following most accurately defines "general insurance business" as per the Insurance Act?
Power of High Court to confirm death sentence is given under Section ……… of CrPC
In which section of Indian Contract Act 1872 provision related to the legal maxim ‘Ex nudo pacto actio non oritur’ is added?
What is the liability of bailee making unauthorized use of goods bailed?
How is the Central Authority expected to operate in the discharge of its functions under the Legal Services Authority Act?
Who has the been vested with the power to establish the Depositor Education and Awareness Fund as per section 26A of the Banking Regulation Act?
Which of the following statements are correct?
The examination of a witness by adverse party is?