Question
If 20 men or 12 boys can complete a job in 25 days, how
long will it take for a team of 15 men and 18 boys to complete the same job? (Calculate approximate value)Solution
According to the question,
20M = 12B
Or, 5M = 3B
Therefore, (15M + 18B) = (9B + 18B) = 27B
12 boys take 25 days to complete the work
Therefore, time taken by 27 boys to complete the work = (12 × 25) / 27 = 11.11 days or 11 days
If 0 ≤ θ ≤ 90°, and sec107 θ + cos107 θ = 2, then. (secθ + cosθ) is equal to:
If (x - 1/x)2 = 3, then the value of x6 + 1/x6 equals
If 2cos2 Ɵ – 5cos Ɵ + 2 = 0,00 < Ɵ < 900 , then the value of (cosec Ɵ + cot Ɵ) is :
If x3 + y3 + z3 = 3(1 + xyz), P = y + z – x, Q = z + x – y and R = x + y – z, then what is the value of P...
If 2y cos θ = x sin θ and 2x sec θ - y cosec θ = 3, then the value of x2+ 4y2 is
...If 3x + 5y + 7z = 49 and 9x + 8y + 21z = 126, then what is the value of y?
The value of = 3/4 ÷ 3/4 of 4/3 + 5/2 ÷ 2/5 of 5/4 – (2/3 + 2/3 of 5/6) is :
The simple interest accrued on a sum at the rate of 10% p.a. for two years is Rs. 5,000.
Quantity I – What will be the compound interest on...
The expression of (cot θ + cosec θ −1) / (cot θ − cosec θ+1) is equal to
Quantity I – 3
Quantity II – 254
If > 0 and < 0