📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    ‘A’ is 20% more efficient than ‘B’. ‘A’ and

    ‘B’ work together for 6 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 6 more days to finish the work. If ‘A’ alone could’ve finished the whole work in 20 days, then find the time taken by ‘C’ to finish 60% work alone.
    A 18 days Correct Answer Incorrect Answer
    B 12 days Correct Answer Incorrect Answer
    C 15 days Correct Answer Incorrect Answer
    D 20 days Correct Answer Incorrect Answer
    E 24 days Correct Answer Incorrect Answer

    Solution

    Let the efficiency of 'B' be 'x' units/day So, efficiency of 'A' = x × 1.2 = '1.2x' units/day Total work = 20 × 1.2x = '24x' units So, work done by 'A' and 'B' together in 6 days = (x + 1.2x) × 6 = '13.2x' units So, remaining work = 24x - 13.2x = '10.8x' units So, efficiency of 'B' and 'C' together = 10.8x ÷ 6 = '1.8x' units per day So, efficiency of 'C' = 1.8x - x = '0.8x' units/day So, required time = (24x × 0.6) ÷ 0.8x = 18 days 

    Practice Next

    Relevant for Exams:

    ask-question