Question
'B' alone can complete a work in 16 days while 'A' and 'B' together can complete the same work in 8 days. 'A' alone started the work and left after 4 days and rest of the work is completed by 'B' alone. If total payment is Rs. 8,000, then find the wages received by 'A'.
More Time and work Questions
- A and B together, B and C together and A and C together can complete a piece of work in 44 days, 33 days and 36 days respectively. Find the ratio of the ef...
- 40 men can complete a piece of work in 40 days. ‘x’ men started the work and after 30 days 64 more men joined them so that whole work was finished in the d...
- Two pipes, P and Q, can fill a tank in 60 minutes and 100 minutes, respectively. A third pipe R can empty it in 1 hour 40 minutes. Initially, pipes P and R...
- A, B and C can complete a work in 10, 20 and 15 days respectively. A left the work 3 days before the work was completed and B left 1 days after A had left....
- 6 interns together do as much work as a regular employee. If 36 interns finish 90 tasks in 3 days, how many regular employees are required to do 90 tasks i...
- A kennel has 40 dogs, and the food available is enough for 15 days. If 10 more dogs are added, how long will the food last?
- A man, a woman, a boy, and a girl can complete a certain task individually in 84 days, 105 days, 140 days, and 210 days respectively. How long will it take...
- A, B, and C can finish a job in 12, 15, and 18 days, respectively. They collaborate to complete the task and receive a combined payment of Rs. 592 for thei...
- In a retreat, there is sufficient food for 300 people for the duration of the retreat. After 8 days, 100 people leave the retreat. Then, after another 3 da...
- Kabir can build a fence in 16 days. Working together, Kabir and Arjun can finish it in 8 days. How long will Arjun take to build the fence alone?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)