⚡ Rakhi Special - Flat 52% off on All Courses from 6 to 10 Aug! ⚡ Enroll Now

    Question

    ‘X’ can finish 50% of a job in 8 days. ‘Y’ takes

    8 days more than ‘X’ to complete the entire work, and Y is 20% more efficient than ‘Z’. ‘X’ starts the task alone, on 2nd day he is joined by ‘Y’ only, on 3rd day, he is joined by ‘Z’ only, and on 4th day, he again works alone. They follow this same pattern for 9 days. The combined time taken by ‘X’ and ‘Y’ alone to finish the leftover work is how much percent more/less than that by ‘Z’ alone?
    A 10% less Correct Answer Incorrect Answer
    B 15% more Correct Answer Incorrect Answer
    C 25% less Correct Answer Incorrect Answer
    D 32% more Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    Time taken by X to complete the work = 8 / 0.5 = 16 days Time taken by Y = 16 + 8 = 24 days Time taken by Z = 24 × 1.20 = 28.8 days Let total work = 576 units Efficiency of X = 576 / 16 = 36 units/day Efficiency of Y = 576 / 24 = 24 units/day Efficiency of Z = 576 / 28.8 = 20 units/day Work done in 3 days = 36 + 24 + 20 = 80 units Work done in 9 days = 80 × 3 = 240 units Remaining work = 576 – 240 = 336 units Time by X = 336 / 36 = 9.33 days Time by Y = 336 / 24 = 14 days Time by Z = 336 / 20 = 16.8 days Required % = ((9.33 + 14 – 16.8) / 16.8) × 100 = 15% more

    Practice Next
    ask-question