Question
The time taken by ‘A’ to complete a task is 6 days more than the time taken by A and B together. If A is twice as efficient as B, find the time required by B to complete the work alone.
More Time and work Questions
- A work can be completed by ‘A’ and ‘B’, alone in 10 days and 15 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- Anil and Ashish receive Rs.2000 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- If ‘P’ can complete a task in 24 days and ‘P’ with ‘Q’ together can finish it in 15 days, then how many days will ‘Q’ take to complete the work alone?
- Deepak and Deepti with each other can complete a work in 60 days, Deepti and Danny in 90 days and Deepak and Danny in 90 days. In how many days can Deepak...
- The ratio of the efficiency of A, B and C is 3:4:5, if they can complete a work in 18 days then A can complete 60% of the work in how many days?
- If 'A' needs 24 more days to complete a certain task working alone compared to when 'A' and 'B' work together, and 'A' is 50% more efficient than 'B', what...
- Choose the statements that correctly show two workers taking 6 hours and 9 hours to complete a task, respectively.
- Amit is 66(2/3)% more efficient than Vivek who can do the same work in 25% more time than Sameer. If Amit and Sameer together can complete 70% of work in 1...
- ‘A’ is 50% more efficient than ‘B’. ‘A’ and ‘B’ work together for 6 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 6 more days to finis...
- Priya completes 30% of a task in 9 days. Her efficiency is 50% greater than Meera's. How many days will it take for both Priya and Meera, working together,...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt