Question
Vikas does 65% of a job in 39 days, while Suman does 40% in
40 days. Vikas worked for 18 days and left. Calculate how many days Suman would need to wrap up the remaining task.Solution
ATQ,
Vikas’ full-time = 39 / 0.65 = 60 days
Suman’s full-time = 40 / 0.40 = 100 days
Total work = LCM(60, 100) = 300 units
Vikas’ efficiency = 300 / 60 = 5 units/day
Suman’s efficiency = 300 / 100 = 3 units/day
Work done by Vikas = 18 Ă— 5 = 90 units
Remaining work = 300 - 90 = 210 units
Time by Suman = 210 / 3 = 70 days
The pressure system is characterized by circular or elliptical isobars with the lowest pressure at the center is called
Which one of the following is used as biofertilizer in non leguminous crops?
The Raphanobrassica hybrid resulted from crossing:
What is the branch of soil related with the origin and classification of soil?Â
Name of the insect Order in which (in general), the larval stage is phytophagous and adults are nectar feeder/sap suckers:
Which type of maize is mainly grown in India?
Which out of following is not a dicotyledon seed?
Viral and mycoplasma infections are known to cause reduced vigor and stunting in plants. However, an application of spray overcomes stunting and axillar...
During the embryogenesis, the cell elongation and cellular differentiation occurs inÂ
Which soil texture class has the highest porosity?