Question

Vikas does 65% of a job in 39 days, while Suman does 40% in 40 days. Vikas worked for 18 days and left. Calculate how many days Suman would need to wrap up the remaining task.

A 70 days
B 61 days
C 52 days
D 35 days
E None of these