Question
Alok finishes 60% of a project in 30 days, while Neha
finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by Neha to complete the remaining project.Solution
ATQ,
Alok’s total time = 30 / 0.60 = 50 days
Neha’s total time = 15 / 0.20 = 75 days
Total work = LCM(50, 75) = 150 units
Efficiency of Alok = 150 / 50 = 3 units/day
Efficiency of Neha = 150 / 75 = 2 units/day
Work done by Alok = 25 × 3 = 75 units
Remaining work = 150 - 75 = 75 units
Time by Neha = 75 / 2 = 37.5 days
Select the set in which the numbers are related in the same way as are the numbers of the following sets.
(NOTE : Operations should be performed ...
What will come in the place of '?' in the following equation, if '+' and - ' are interchanged and '×' and '÷' are interchanged?
729 × 81 – 9...
Read the given statements and conclusions carefully. Assuming that the information given in the statements is true, even if it appears to be at variance...
A series is given with one term missing. Select the correct alternative from the given ones that will complete the series.Â
OP, ON, MN, ML, ?Â
Select the correct mirror image of the given figure when the mirror is placed at MN as shown below.
Â
What letter will come in place of question mark?
B F Q
U C A
M ? H
What is the median of 5, 2, 7, 8, 1 and 4?
In a certain code language, ‘ZERO’ is coded as ‘2468’ and ‘OILY’ is coded as ‘5679’.
What is the code for ‘O’ in that languag...
Complete the series by replacing the question mark (?).
Q331T, U442X, Y553A, ?