Question
Alok finishes 60% of a project in 30 days, while Neha
finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by Neha to complete the remaining project.Solution
ATQ,
Alok’s total time = 30 / 0.60 = 50 days
Neha’s total time = 15 / 0.20 = 75 days
Total work = LCM(50, 75) = 150 units
Efficiency of Alok = 150 / 50 = 3 units/day
Efficiency of Neha = 150 / 75 = 2 units/day
Work done by Alok = 25 Ă— 3 = 75 units
Remaining work = 150 - 75 = 75 units
Time by Neha = 75 / 2 = 37.5 days
Name the training system in which the main stem is allowed to grow only up to a certain height of about 1.5 to 1.8 m and then it is cut for development ...
The Headquarters of International Rice Research Institute is located at
Where does India rank in production of fruits in the world ?
Another term for provitamin is:
Choose the correct option
Statement I. Drought do not occur in Assam, south Kerala and Eastern parts of West Benagl
Statement II. Aridity ...
Who is the present Union minister for Agriculture and Farmers' Welfare ?(Jan 2024)
Which of the following statements about weathering is false?
Soil health card with the tagline “Swasth Dharaa, Khet Haraa” was launched on ____.Â
The Germination percentage in onion in case of certified seeds isÂ
 "What nutrient deficiency is responsible for interveinal chlorosis?"