Question
Alok finishes 60% of a project in 30 days, while Neha finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by Neha to complete the remaining project.
More Time and work Questions
- A can finish a job in 30 hours while B can finish it in 20 hours. If C is (300/7)% more efficient than A and B together, then find the time taken by C alon...
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- ‘A’ and ‘B’ can do a piece of work in 30 days and 20 days, respectively. If they started the work together and worked on it for 4 days, then find the time ...
- Rohan can finish a task alone in 24 days. Shreya can do 50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% of ...
- Amisha is 50% more efficient than Khushi. Amisha started a work, worked for 'w' days and then Khushi replaced Amisha. khushi completed the remaining work i...
- A buffalo alone can plough field ‘A’ in 20 days. A Bull alone can plough the field ‘A’ in 10 days. Find the number of days taken by 1 bulls and 4 buffalo t...
- It takes a team of either 20 boys or 35 girls, 27 days to achieve a sales target. How many days will it take for a team consisting of 21 boys and 42 girls ...
- 3 men and 1 boy together can complete a work in 20 days. 2 men and 3 boys can together complete half of the same work in 10 days. Find the time taken by 1 ...
- There is enough food in a camp to last for 50 days if each of the 40 soldiers present at the camp eat 2 times a day. After 20 days, 40 more soldiers joined...
- A tank can be filled by pipe A in 6 hours and by pipe B in 8 hours. There is also a waste pipe C which can empty the full tank in 12 hours. If all three pi...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt