Question
Alok finishes 60% of a project in 30 days, while Neha
finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by Neha to complete the remaining project.Solution
ATQ,
Alok’s total time = 30 / 0.60 = 50 days
Neha’s total time = 15 / 0.20 = 75 days
Total work = LCM(50, 75) = 150 units
Efficiency of Alok = 150 / 50 = 3 units/day
Efficiency of Neha = 150 / 75 = 2 units/day
Work done by Alok = 25 × 3 = 75 units
Remaining work = 150 - 75 = 75 units
Time by Neha = 75 / 2 = 37.5 days
The micronutrient that is most cruical for Nitrogen metabolism in pulses is
Internal browning in fresh produce is the result of:
At temperatures above freezing, activities of food borne microorganisms can be:
According to the APEDA Act, which of the following is included in the second schedule?
Which of the following is not a function of FSSAI?
Variations in moisture content result in the clay soil's characteristic swelling and shrinking. It is due to presence of ____________ mineral.
An area having Nutrient index> 2.33 will be
Amount of water in 5 ha cm will be
What is the electrical conductivity of saline soil?
Which of the following is NOT among the main objectives of secondary tillage operations?