Question
Alok finishes 60% of a project in 30 days, while Neha
finishes 20% of the same in 15 days. Alok worked for 25 days and then stopped. Find the time taken by Neha to complete the remaining project.Solution
ATQ,
Alok’s total time = 30 / 0.60 = 50 days
Neha’s total time = 15 / 0.20 = 75 days
Total work = LCM(50, 75) = 150 units
Efficiency of Alok = 150 / 50 = 3 units/day
Efficiency of Neha = 150 / 75 = 2 units/day
Work done by Alok = 25 × 3 = 75 units
Remaining work = 150 - 75 = 75 units
Time by Neha = 75 / 2 = 37.5 days
 Kautilya in his Arthashastra describes the availability of varieties of pearls from the
Which of the following is an example of a living fossil tree?
The government has extended the Pradhan Mantri Krishi Sinchayee Yojana (PMKSY), launched in 2015 to improve farm productivity by four years till ______...
Which among the following is not a crypto currency ?
Sodium deficiency can occur in which of the following conditions?
Â
In the upper reaches of the atmosphere, a molecule containing three atoms of oxygen is found. This forms a layer called:
Consider the following statement about MAHASAGAR:
1. It is initiative of the Indian Army
2. The maiden edition of the high level virtual i...
What is the total railway track length in India?
Which DPSP emphasizes the importance of providing adequate means of livelihood to all citizens and preventing the concentration of wealth and resources ...
Who among the following called the Revolt of 1857 a ‘National Revolt’?