Question

    ‘A’ and ‘B’ together can

    complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 10 days. If ‘B’ takes 5 days to complete the work alone then find the time taken by all three together to complete 57.5% of work.
    A 23 days Correct Answer Incorrect Answer
    B 25 days Correct Answer Incorrect Answer
    C 21 days Correct Answer Incorrect Answer
    D 20 days Correct Answer Incorrect Answer
    E 26 days Correct Answer Incorrect Answer

    Solution

    Let the total work = 40 units Efficiency of (A + B) = 40/8 = 5 units/day Efficiency of (B + C) = 40/10 = 4 units/day Efficiency of ‘B’ = 40/5 = 8 units/day Efficiency of (A + B + C) = (5 + 4 – 8) = 1 units/day Required time taken = (0.575 × 40)/1 = 23 days

    Practice Next