📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      A alone can finish the work in 10days and B alone can

      finish the same work in 15 days. All A, B and C together take 5 days to finish the work. Find the time in which the same work can be completed in a sequence such that A starts first then B and then C.
      A 15 Correct Answer Incorrect Answer
      B 12 Correct Answer Incorrect Answer
      C 9 Correct Answer Incorrect Answer
      D 18 Correct Answer Incorrect Answer
      E None of the above Correct Answer Incorrect Answer

      Solution

      Total amount of work = LCM(10,15,5) = 30 Efficiency of A: 30/10 = 3units/day Efficiency of B: 30/15 = 2units/day Efficiency of A+B+C = 5 units/day => Efficiency of C=6-3-2=1 unit/day Work done by A+B+C together in 3 days = (3+2+1)×1 = 6 unit Total number of days required to finish the work: 30/6 => 5×3 = 15 days

      Practice Next

      Relevant for Exams:

      ask-question